Exclusive by Tim Wood
A groundbreaking ruling by an adjudicator that the costs of a claim
involving a subcontractor and a contractor were to be met by the
defendant could have "far-reaching consequences" for the
construction industry, a solicitor involved in the case has warned
this week.
The adjudicator ruled in favour of subcontractor John Cothliff Ltd
after it brought a case against building contractor Allen Build
(Northwest), claiming it was owed money following the completion of
work for the company.
The Housing Grants Construction and Regeneration Act 1996 applies
to most construction contracts made after May 1998 and imposes
certain provisions in relation to payment disputes. The provisions
include a mandatory 28-day adjudication scheme to offer a quick
method of resolving disputes in the construction industry and that
the adjudicator's decision is binding, unless and until it is
finally determined either in arbitration or by the courts.
But in the historic hearing at Liverpool Technology and
Construction Court on 29 July, the adjudicator effectively ordered
that Allen Build must pay the costs, even though the firm protested
that the court had "no power to do so" under the Act.
Solicitor Hill Dickinson represented John Cothliff in the
case.
David Chinn, head of its construction unit, said: "The court's
decision has far-reaching consequences, particularly where a
claimant spends significant time and resources in preparing its
case for adjudication, or where a claimant wishes to engage its
legal representatives on a conditional basis.
"However, this case related to an adjudication under the statutory
scheme and therefore it may still be open to the parties to agree
that the adjudicator shall have no power to make decisions in
relation to costs incurred by them during the adjudication."