Potential bill of £70m-£100m likely for end of lease and
move to new building Exclusive by Carol Millett
The Home Office's decision to build new headquarters rather than
refurbish its present headquarters at Queen Anne's Gate could cost
the taxpayer an extra £160 million, Contract Journal learned
this week.
The Home Office's original tender called for a £60 million
refurbishment of its Queen Anne's Gate offices. This would have
involved a double decant of 1,500 Home Office officials to
temporary quarters refurbishment took place.
But an innovative bid from a consortium led by developer Godfrey
Bradman, which proposed a new building on the site of the former
departments of transport and the environment at Marsham Street,
prompted the Home Office in April to ask the three shortlisted
bidders to start re-tendering in September. The three - Bradman,
Bovis and Jarvis - are using Bradman's original proposal as a
blueprint. All three are being compensated for the rebid.
Ministers and Home Office officials opposition to the prospect of a
double decant under the original proposal prompted the rebid.
Bradman's solution requires officials to only move once.
But Contract Journal learned this week that the new proposals will
incur up to an extra £160 million in costs. The new-build
project will cost £120 million, which includes the cost of
demolishing the triple-tower Marsham Street building. And the Home
Office will have to pay property company Land Securities, which was
one of the bidders on the original proposal, between £70-100
million to get out of its existing lease on Queen Anne's Gate,
which has another 18 years to run.
A source revealed: "The concern was that a double decant was too
disruptive for Home Office officials who wouldn't know where to go
for lunch. So instead of paying £60 million for the refurb of
Queen Anne's Gate, they are now paying for a £120 million
project and between £70-100 million to get out of its lease
with Land Securities."
A Home Office spokeswoman said: "No decision has been taken on the
future of Queen Anne's Gate. If the decision had been taken to stay
in the building, it would have cost millions to maintain it and
that would have been needed now. Also a double decant would cost a
substantial amount on top of the £60 million. So it is not as
simple as it appears."
Ian Henderson, head of Land Securities, said: "The Home Office has
been negotiating a break clause in its lease." He said that these
negotiations are ongoing but he could not go into any details
because they were "commercially sensitive."