A body of case law is slowly but steadily being established to
clarify the adjudication process. The trend has been for the court
to robustly enforce the decision of adjudicators on the basis that
this was what Parliament intended. Even when an adjudicator failed
to provide a good answer, it will be treated, nevertheless, as one
capable of enforcement since it is not necessarily the final
answer.
All has not been plain sailing, however. In the Project Consultancy
Group -v- The Trustees of The Gray Trust the head of the Technology
and Construction Court, The Hon Mr Justice Dyson QC, refused to
enforce the decision of an adjudicator on the basis that it was at
least arguable that the parties had not entered into a construction
contract within the meaning of the Housing Grants, Construction and
Regeneration Act 1996.
Previously, in Macob Civil Engineering -v- Morrison Construction,
Justice Dyson examined Section 108(3) of the Act where it states:
"The contract shall provide that the decision of the adjudicator is
binding until the dispute is finally determined by legal
proceedings, by arbitration... or by agreement." He held the word
"decision" in this section of the Act should be given its plain and
ordinary meaning and that a decision whose validity was challenged
was nevertheless a decision within the meaning of the Act and the
Scheme.
In Macob, the adjudication decision was challenged on the basis
that there had been a procedural error by the adjudicator which
amounted to a breach of natural justice. On this Mr Dyson said: "If
his decision on the issue referred to him is wrong, whether because
he erred on the facts or the law, or because in reaching his
decision he made a procedural error which invalidates the decision,
it is still a decision on the issue. Different considerations may
well apply if he purports to decide a dispute which was not
referred to him at all."
It was this last sentence which became relevant in the present
case. Different considerations must indeed apply where the
adjudicator purports to make a decision which he is not empowered
by the Act to make.
An example would be where an adjudicator decides a dispute arising
under a contract which is not a construction contract within the
meaning of the Act. Another example would be where the contract
does not come within reach of Section 108 of the Act because,
although it is a construction contract, it was entered into before
the commencement of the Act, being 1 May 1998.
The Project Consultancy Group carried out professional design
services in connection with the conversion of a property into a
nursing home for the Trust. It alleged the non-payment of fees, and
sought the appointment of an adjudicator to decide the matter. The
Trust's solicitors responded saying that the contract had been
entered into in March 1997 and argued that the Act could therefore
not apply and that the Notice of Reference to Adjudication was
invalid.
Nevertheless, the Project Consultancy Group proceeded to obtain the
appointment of an adjudicator. In its response document the Trust
stated that it disputed the contractual position and that this
would impact upon the adjudicator's jurisdiction to determine the
matter. It argued that the contract was a pre-May 1998 contract and
that the adjudicator had no jurisdiction to decide the
dispute.
It is not surprising to find the parties arguing over the date of
the contract. The procurement process for construction projects is
at best an untidy mess. It is commonplace for formal contract
documents never to be executed. Parties will progress projects on
the basis of loosely worded Orders or Letters of Intent, such that
it will often be difficult, if not impossible, to establish the
true nature of the transaction. A very large proportion of
construction disputes which are heard in front of the courts or
arbitrators commence with argument as to whether there was a
contract, and if so, when it came into force and what were its
terms.
Despite these difficulties the adjudicator decided that there was a
contract entered into after May 1998 capable of being regarded as a
construction contract within the meaning of the Act, and
accordingly he proceeded to make his decision that fees in the sum
of approximately £65,000 were due to the Project Consultancy
Group.
As expected, the Trust refused to observe the adjudicator's
decision and the Project Consultancy Group applied for enforcement
of the decision upon summary judgment pursuant to Part 24 of the
new Civil Procedure Rules.
Justice Dyson was in no doubt that it would be open to a defendant
in enforcement proceedings to challenge the decision of an
adjudicator on the grounds that he was not empowered by the Act to
make the decision. The only real question to decide, however, was
whether, by participating in the adjudication process, the Trust
had waived this jurisdiction point and agreed to abide by the
decision of the adjudicator on that issue. Previous custom and
practice in connection with arbitrators was unhelpful in the view
of the judge. He was satisfied that in its initial communications
and in its response to the adjudicator, the Trust had never
departed from the position that the contract was not one caught by
the provisions of the Act. It did not submit to the jurisdiction of
the adjudicator on this point.
The adjudicator could not, simply by issuing his decision, create
jurisdiction where none existed in the absence of clear agreement
between the parties.
In defending the application for enforcement the Trust needed only
to show in the summary proceedings that there was a reasonable
prospect that it could demonstrate in full trial that there was no
contract capable of giving jurisdiction to the adjudicator.
The Judge was satisfied that there was reasonable evidence to doubt
whether a contract had been formed at all. Accordingly, the
application for enforcement of the adjudicator's decision was
dismissed.
INBRIEF
The Case:
Project Consultancy Group -v-The Trustees of The Gray Trust, TCC,
16 July 1999.
The Issue:
Enforcement of adjudicator's decision.
The Implication:
Failure to establish on clear evidence the existence of a contract
within the meaning of the Construction Act will deny a party the
means of conferring the necessary jurisdiction upon an adjudicator.