At present the reported cases concerning the enforcement of the
decisions of adjudicators point to one conclusion. Enforcement will
be given unless it can be shown by the opposing party that the
adjudicator lacked the necessary jurisdiction to make his decision.
The approach normally taken by adjudicators when there is a
challenge to their jurisdiction will be to investigate the
contentions being made and if in their view the challenge is
unjustified, they will proceed with the adjudication. This is not
to say, however, that the adjudicator is empowered to decide the
matter of his jurisdiction. He may proceed according to his own
findings but it leaves the parties free to continue their challenge
to the jurisdiction if they so wish.
A party opposing jurisdiction has a number of options it might
take. First and foremost, if the adjudicator elects to proceed with
the adjudication, the opposing party must continue to declare its
opposition to the jurisdiction as it will not wish its
participation in the adjudication process, by for example
submitting a case in defence to the adjudicator, to be seen as an
acceptance of the jurisdiction point.
That party may choose to wait until the adjudicator's decision is
made, refuse to comply with the decision, and then oppose any
enforcement proceedings on the basis that the adjudicator lacked
jurisdiction.
Alternatively it is possible for either party to obtain a binding
ruling upon the question of jurisdiction concurrently with the
adjudicator dealing with the substantive issues. In Palmers Limited
-v- ABB Power Construction Limited a declaration on the matter of
whether the adjudicator had the necessary jurisdiction was obtained
from the Technology and Construction Court in a few days and while
the adjudication was proceeding.
Another alternative, if the construction contract contains an
arbitration clause, is for the parties to seek a decision upon the
adjudicator's jurisdiction by reference to an arbitrator. Parties
who immediately think that this would result in a 12-18 month delay
to the process, based upon their hard bitten past experience of
arbitration need not worry. The Dispute Resolution Service of the
Royal Institution of Chartered Surveyors is offering an arbitral
appointment procedure to deal with such matters with a promise that
an award upon the matter of jurisdiction of an adjudicator can be
made within 48 hours of the appointment of the arbitrator under its
scheme. This may be regarded as an extremely cost effective
approach to take.
The primary area of challenge to jurisdiction will concern the
existence of the underlying contract or the date by which that
contract may be said to have come into force. In the construction
industry we tend to allow the most appalling uncertainty and
confusion to surround the procurement process and disputes over the
existence of a contract are commonplace. Since the Act can only
apply to written contracts made after 1 May 1998 it is no surprise
that this remains a fertile area for dispute.
It is common practice for works to commence on the basis of a loose
agreement embodied within a letter of intent, where formal contract
documentation is concluded at a later date. Where the commencement
date precedes 1 May 1998 and the formal contract is put in place
after that date, doubts can arise.
In the 1963 case of Trollope & Colls -v- Atomic Power
Constructions Limited it was held that the contract, once made,
would have retrospective effect to govern the relationships of the
parties prior to that date. In such a case however, the contract
would nevertheless be made after 1 May 1998 and its retrospective
effect would not alter its status in respect of the Construction
Act. Even where it could be said that the earlier letter of intent
was itself a contract having a full and binding effect between the
parties, the later contract may be regarded as superseding that
earlier arrangement and thus the Construction Act would still bite
in respect of any disputes then arising.
Some of these matters were recently examined in the case between
Atlas Ceiling & Partition Company Limited -v- Crowngate Estates
(Cheltenham) Limited, where an adjudicator's decision was resisted
upon enforcement on the basis that the contract predated 1 May
1998. Atlas brought evidence to show that despite having agreed
articles of agreement relative to a DOM/2 subcontract in April
1998, there was evidence to show that the parties had not intended
to enter into legal relations until agreement on further points had
been made.
Judge Thornton agreed with this contention, held that the
adjudicator had the necessary jurisdiction, and ordered that
judgment be given for the sum found by the adjudicator to be due.
The approach of Judge Thornton was however, remarkable. He ordered
that the summary judgment application be transformed into a trial
of the issue of the adjudicator's jurisdiction in open court,
including the cross-examination of the parties' witnesses.
The speed in which this was able to happen was also remarkable. The
parties had their answer within 18 days of the commencement of the
proceedings. Two years ago this would have been thought of as
justice at the speed of light.