The Privy Council is the final court of appeal for disputes
emanating from Commonwealth jurisdictions, and carries out its
duties in a similar manner to the House of Lords.
Very recently the Privy Council was asked to consider the manner in
which damages would be assessed in relation to an action brought in
the tort of negligence. In this particular case the damages
incurred by the plaintiff had greatly escalated as a result of the
plaintiff's inability to put right defects until the court case had
been concluded in its favour.
Alcoa Minerals of Jamaica Inc owned a smelting plant which was
alleged to have generated and dispersed into the atmosphere
pollutants, noxious gases and corrosive dust. Herbert Broderick
owned a property in the neighbourhood of the plant and complained
that omissions had caused corrosion to the galvanised zinc panels
of the roof of his house.
When the damage first occurred he repaired it, but by 1989 the
damage had occurred again and he was not able to pay for the
necessary repairs. In 1990 he commenced proceedings against Alcoa
Minerals and calculated his damages for the cost of repairing the
roof at $211,000 Jamaican dollars.
It seems that litigation in Jamaica is no faster than litigation in
England, and by 1994 a judgment had still not been obtained. The
cost of repairing the building had however, dramatically increased
largely due to rapid inflation and the fall in the value of the
Jamaican dollar. In March 1994 the court allowed Broderick to amend
the amount of his claim to approximately $938,000.
Eventually in early 1995 the court found for Broderick and awarded
him the full amount of the increased sum claimed. Alcoa Minerals
complained bitterly to the Court of Appeal that they should not be
liable for the higher figure and that the original figure was
correct. That was the cost of repair at March 1990 when the
physical damage had occurred and it was this lower sum, and no
other, to which they should be held accountable.
The Court of Appeal accepted that the general rule in tort was that
damages should be assessed at the date of the breach. This was a
principle clearly enunciated by Lord Wilberforce in the Court of
Appeal in 1976 in the case of Miliangos -v- George Frank (Textiles)
Ltd, but Lord Wilberforce had made it clear that the rule was
subject to exceptions. In particular, where that rule would produce
injustice, the court had a discretion to take some other date for
assessment of damages.
The Court of Appeal of Jamaica had also considered the 1933
decision in Liesbosch Dredger -v- Edison. The Liesbosch was a
dredger doing construction work under a contract with heavy
penalties for delay. The dredger's moorings were fouled by the
Edison and consequently the dredger sank.
The dredger's owners could not purchase another dredger because of
want of funds, and so instead a replacement dredger was hired. They
were awarded as damages the market price of a comparable dredger on
the day the Liesbosch sank, together with the cost of adapting it
and transporting it to the site. It was held that they were not
entitled to the cost of hiring which was categorised as a separate
head of damage arising due to a separate cause, namely the owner's
lack of funds for which the defendants could not be held liable.
In the present case the Court of Appeal held that the Liesbosch
decision depended on a different set of facts. In particular
Broderick was not seeking different heads of damage. There was only
one head of damage, namely the cost of repairing the building. The
need to repair the roof was a direct consequence of the negligence
of Alcoa Minerals and the real question was therefore whether
Broderick was in breach of his duty to mitigate his damage. The
Court of Appeal decided that Broderick was fully entitled to wait
until the outcome of the litigation was known before proceeding
with repairs and therefore he was not in breach of any requirement
to mitigate.
The Privy Council reviewed these matters. They concluded that it
seemed to have been obviously foreseeable that if the house of a
person in a position of the plaintiff was seriously damaged, he
would not or might not have the wherewithal to repair it.
Furthermore, it was foreseeable that his ability to repair might
depend on his establishing liability and recovering damages from
the defendant. Even assuming that Broderick could have raised a
loan, by waiting and not borrowing money at a high rate of interest
for some six years he was not in breach of his duty to mitigate.
It was concluded that Broderick had behaved reasonably by waiting,
if indeed he had any realistic choice to do anything but wait,
until money was available from Alcoa Minerals. He needed to be
reasonably sure that Alcoa would pay or be liable before he did the
repairs. That took time and there had been no evidence to suggest
that the delay in obtaining the judgment was the fault of
Broderick.
There was no question of Broderick deliberately delaying doing the
repairs so as to increase Alcoa Mineral's liability. The Privy
Council also recognised that there was no windfall in this process
for Broderick. On the contrary, it would be a hardship for
Broderick not to get the cost of repairs actually expended.
In conclusion the Privy Council affirmed the award of special
damages of the Court of Appeal in favour of Broderick in the amount
calculated from the point at which liability had been established.