The High Court has given fresh guidance on the rights of parties to
launch adjudication when other moves are already underway to
resolve the dispute.
Last week in the Technology and Construction Court, Mr Justice
Dyson rejected claims by Breen Property that Herschel Engineering
was not entitled to seek adjudication in a dispute over payment for
electrical and other work carried out on a property in London,
SW7.
An adjudicator had awarded £17,355 to Herschel but Breen
claimed that the adjudication should have been blocked. Breen
argued that the adjudication should not have taken place because of
county court proceedings, which were brought against the property
company by Herschel and which were subject to a pending
appeal.
Dyson said Breen claimed that the court should not countenance two
concurrent proceedings in respect to the same course of action.
He dismissed Breen's challenge and granted summary judgment to
Herschel in respect to the sum awarded by the adjudicator. Dyson
ruled that he did not accept that the provisions under which the
adjudication were brought required a reference to adjudication to
be made before litigation or arbitration proceedings were
commenced. Nor did Dyson consider that such proceedings should not
start until after completion of adjudication.