Bovis Lend Lease has failed in a High Court move to bring an early
end to a multi-million pound claim it has launched against client
Braehead Glasgow over the Braehead shopping centre.
Bovis had sought immediate judgment in respect of two claims
totalling over £8.8m, but Mr Justice Dyson dismissed the move
because he considered Braehead had a real prospect of successfully
defending the case. He said: "I am not satisfied that, if the claim
went to trial, Bovis would obtain judgment for a substantial, or
indeed any, amount from Braehead."
However, he said that Braehead claimed, among other things, that it
was entitled to set off a counterclaim for damages for breaches of
contract and that it had provisionally quantified the damages as
exceeding £16m. Braehead alleged that Bovis had failed to
properly manage the work or exercise proper cost control and was
responsible for extensive defective work. Bovis argued the claims
for damages were "wholly without foundation".
Braehead also claimed it was arguably entitled to deduct liquidated
and ascertained damages (LADs) of almost £7m for late
completion. Dyson said that he considered Braehead had an arguable
entitlement to deduct LADs in the sum of £6.64m.
Dyson added that Braehead's counterclaim contained more than 150
separate allegations and he was convinced that Braehead had a real
prospect of succeeding on its counterclaim to a substantial
extent.
The judge commented: "Bovis knew that the two valuations were not
met by Braehead because of Braehead's concern about the massive and
unexpected increases in cost and the time overrun that became
apparent in 1999. In December 1999 and January 2000, sensible and
constructive proposals were being discussed between the parties as
to how to resolve their differences. For a reason which has not
been explained to me, Bovis decided to resort to litigation rather
than seek to negotiate further with Braehead."