There is a well established line of legal authority to the effect
that a party should not normally make the same claim against
another party in two or more different legal proceedings.
To allow the party to do this would be oppressive and unjust to the
other party. It would give rise to the risk of inconsistent
findings by different tribunals on the same issue or issues. This
principle is most typically applied in relation to concurrent
proceedings in different courts. It is also applied however, in
relation to concurrent court and arbitration proceedings.
In the 1912 case of Doleman & Sons v Ossett Corporation,
litigation had been started on a contract which contained an
arbitration clause. While these legal proceedings were continuing,
and without the consent of the Plaintiff, an arbitrator made an
award on the very subject matter of the action. It was held by
majority in the Court of Appeal that the court was seized of the
dispute and that it was by its decision alone that the rights of
the parties were to be settled. It was said that there could not be
two tribunals each with jurisdiction to insist on deciding the
rights of the parties and to compel them to accept its decision. If
the matter were otherwise there would be a race between the court
and the other tribunal as to which should be the first to give its
decision. This would be "ousting the jurisdiction of the court in a
most ignominious way".
The case of Herschel Engineering Ltd v Breen Property Ltd examined
whether the same principles would apply to a construction
adjudication commenced concurrently with legal proceedings.
Herschel was engaged by Breen to provide electrical and other
works at a property in Cornwall Gardens, London. It was not in
dispute that the contract between the parties was a 'construction
contract' within the meaning of section 104 (1) of the Housing
Grants, Construction and Regeneration Act. The contract did not
comply with the requirements of the Act in respect of adjudication
and accordingly the provisions of the Scheme for Construction
Contracts applied.
A dispute arose concerning the non-payment of two invoices
submitted by Herschel, who commenced proceedings in the County
Court seeking judgment for the amount of the two invoices. While
these proceedings were continuing the question of a possible
reference of the disputes to adjudication was raised by Herschel
before the District Judge. The court made an order including a stay
of the proceedings for 28 days "for adjudication to be
considered".
Meanwhile, Herschel had given notice of its intention to refer to
adjudication the disputes arising from the non-payment of the two
invoices that were the subject of the County Court proceedings.
Breen characterised such action as an abuse that would entitle it
to apply for an injunction restraining the adjudication.
Nevertheless, an adjudicator was appointed. Breen did not
participate in the adjudication despite being invited by the
adjudicator to do so. In the event, the adjudicator decided the
issues, quite appropriately, solely on the basis of the material
that had been supplied by Herschel.
Faced with a refusal to pay, Herschel then issued an application
for summary judgement in respect of the sums ordered to be paid by
the adjudicator. Breen defended, arguing it was being vexed,
harassed and put to unnecessary expense by the process of two
actions in respect of the same subject matter. Since the County
Court proceedings were started before the adjudication, Breen
argued the court should have granted an injunction to restrain
Herschel from proceeding with the adjudication. In such
circumstances the court should not now allow enforcement of the
decision.
Breen further argued that by starting proceedings in the County
Court, Herschel had effectively waived or repudiated the benefit of
the adjudicator provisions contained in the contract.
Mr Justice Dyson accepted that the court would not normally
countenance concurrent proceedings in litigation or arbitration. He
could not accept, however, Breen's submission that there was a
close analogy between the position of an arbitrator and that of an
adjudicator. The decision of the adjudicator is not final by
paragraph 23 (2) of the Scheme.
Moreover, the Act expressly states that a party may refer a
dispute to an adjudicator "at any time". Justice Dyson considered
that if Parliament had intended that a party should not be able to
refer a dispute to adjudication once litigation or arbitration
proceedings had been commenced, he would have expected this to be
expressly stated. As for the risk of inconsistent findings of fact,
on any view this is inherent in the adjudication process.
In conclusion, there was no reason why for several months Herschel
should be kept out of the money that the adjudicator decided it
should receive. This would be contrary to the plain intent of the
1996 Act. Accordingly Herschel was entitled to obtain summary
judgment in respect of the adjudicator's decision.
One footnote is relevant. Justice Dyson noted there was no
evidence that if Breen were successful in defending the County
Court proceedings, Herschel would be unable to repay the sum
awarded by the adjudicator. Had the position been otherwise, and
there was a real doubt as to Herschel's ability to repay if it lost
in the County Court, he would probably have granted a stay of
execution pending the final determination of the County Court
proceedings.