Railtrack 'not ditching' £5.4bn WCML
Railtrack has poured scorn on a newspaper report that it is about
to ditch the £5.4bn upgrade of the West Coast Main Line in
favour of a cut-price alternative.
The Guardian reported on Monday (29 May) that Railtrack wanted only
to upgrade the track because it was not able to complete the
£3bn worth of advanced signalling for the route by the 2005
deadline.
A Railtrack spokeswoman said the report was completely unfounded
and that "as far as the Board of Railtrack was concerned, it is
full steam ahead".
Another Railtrack official commented: "We are pressing ahead with
phase one of the programme (the track improvements) and a lot of
work has already been done in the Manchester, Birmingham and Euston
areas. We are also doing a lot of work in other areas as well as
looking at the signalling."