In December of last year I reported the case of Bouygues -v-
Dahl-Jensen. Although the case is soon to be heard on appeal, it
has been cited by many as an illustration of the force and
effectiveness of adjudication under the Housing Grants,
Construction and Regeneration Act 1996.
The parties were approximately £11m apart when an adjudicator
was appointed and given 28 days to resolve their disputes. Having
assessed each party's entitlement on its respective claims and
counterclaims, the adjudicator made a simple but fundamental error
in his final statement of monies payable.
He calculated the monies due to the subcontractor Dahl-Jensen on
the basis of gross amounts taking into account both claim and
counterclaim, and then deducted previous payments, this latter
figure being an amount net of retention. The effect was to release
retention to the subcontractor in circumstances where the parties
accepted that the works were not completed and retention not yet
payable.
The adjudicator awarded a net amount of £207,000 in favour of
Dahl-Jensen. Had the adjudicator spotted his error the overall
effect would have been a net award of £140,000 in favour of
Bouygues. On receipt of the adjudication decision, Bouygues'
solicitors invited the adjudicator to correct the "slip". The
adjudicator refused to do so contending in any event that he was
now functus officio as regards the decision.
The court concluded that in so far as the adjudicator had made a
mistake, it was a mistake in his calculations on the disputes put
before him. It was not a mistaken decision to deal with a dispute
that was outside his jurisdiction. Consequently Dahl-Jensen
succeeded in enforcing the adjudicator's decision despite the
existence of a very clear error.
Similar issues arose in the more recent case between Bloor
Construction -v- Bowmer & Kirkland. Bowmer as main contractor
entered into a contract with Bloor as subcontractor, under which
Bloor was to provide labour and plant for ground works for a
development at Whiteley Village, Fareham, in Hampshire.
Disputes arose under the contract and in early January of this year
Bloor served notice on Bowmer of its intention to refer the
disputes to adjudication. In the event the adjudicator delivered
his decision with the effect that Bloor should be paid
£122,000 including interest within 14 days of the date of the
decision. The adjudicator sent a copy of his decision by fax to the
parties. On receipt of the fax the managing surveyor employed by
Bowmer realised that the adjudicator had failed to take into
account previous payments made by them.
The error was pointed out to the adjudicator, and as a consequence
later that same day the adjudicator sent a second decision to the
parties taking into account the previous payments. The effect was
that the £122,000 was no longer payable to Bloor, but instead
the decision held that, subject to work in progress, Bloor was now
in the position of a small over payment.
In court it was argued on behalf of Bloor that once the adjudicator
had communicated his decision to the parties, his duty was at an
end and he had no power to correct any errors, except perhaps
clerical errors. It was argued that Parliament had laid down a
quick and certain interim procedure for resolving disputes on the
basis that any temporary injustice can be corrected at a later
date. It was said that the adjudicator had a semi-judicial role
which terminated at the delivery of his decision.
Bowmer argued that there must be an implied term in the contract
between the adjudicator and the parties that the adjudicator had a
power to correct manifest errors and clerical errors in similar
fashion to arbitrators.
Judge Toulmin recognised that the Act and the Scheme do not address
the question of whether, and if so in what circumstances, a
decision once taken can be amended. It is therefore solely a matter
of contract and thus, according to Judge Toulmin, the question was
whether or not any terms could be implied into the agreement
between the parties, under which the adjudicator could amend his
award.
Judge Toulmin referred to the 1985 case of The Montan in which an
arbitrator had accidentally transposed the names of the parties. In
this case Sir John Donaldson, the then Master of the Rolls, had
repeated his analysis of the "slip" rule. "It is a distinction
between having second thoughts or intentions and correcting an
award to give true effect to first thoughts or intentions which
creates the problem."
Judge Toulmin was clear that the error in this case fell into the
category of a "slip". The adjudicator was giving effect to his
first thoughts and intentions in his amended ruling. In summary,
Judge Toulmin recommended the contractor include a term that refers
the dispute to adjudication. This additional term would allow the
adjudicator or a third party application to correct an error
arising from an accidental error or omission, to clarify or remove
ambiguity in decisions reached.
He also stated that this would need to be executed within a
reasonable time and without prejudicing the other party.