by John Leitch
Cleveland Bridge, the steel fabrication and bridge-building
business, made a total loss over the past 10 years of £42m - a
strategy of focussing on small contracts left the group unable to
cover its overhead costs.
Kvaerner has sold the company to a management buy-out team led by
chief executive Tony Rae. Seven of Cleveland Bridge's senior
managers raised a total of £7.7m to purchase the company,
which currently has an annual turnover of £125m, the workload
being split between £45m in the UK and £80m abroad.
"Overall, the losses in the last 10 years amounted to £42m but
the group made £50m from its major projects," said Rae last
week. "In other words the smaller contracts were the disaster. When
I joined Cleveland Bridge two-and-a-half years ago as commercial
director we had 20 jobs with an average value of £1m and they
were killed by overheads. Now we have four jobs each worth
£20m."
Rae, who describes himself as "a hard-nosed contractor at heart",
said the mbo had been done without financial assistance from any
venture capital group. "The seven of us have done it with our own
money," he said. "We're committed. Parts of the business were bad,
but Cleveland Bridge is the best bridge builder in the
world."
Rae has plans to double annual turnover to £250m by 2004.
"We're on target for that sort of expansion," he added. He said
that up until now Cleveland Bridge had ignored the biggest market
in the world - the USA. "There's more work in the States on steel
bridges than in the rest of the world."
Cleveland Bridge's most publicised project in the UK in recent
years has been a bridge upgrade on the M5 near Bristol. Costain won
the main contract to improve the stretch of the motorway with a bid
of £50m and awarded the subcontract to strengthen the
Avonmouth Bridge to Cleveland Bridge who priced the work at
£25m.
Rae said Cleveland Bridge's element of the bill would pan out at
£70m, with the final overall cost of the scheme costing the
taxpayer £150-200m. While he described the project as "a mess
as a total job" he added "what we've done is an engineering
triumph".
"We bid against a set of documents that bore no resemblance to
actuality," said Rae. "We've handled a total of 9,000t of steel -
but in 130,000 pieces. That's crazy. On other bridges, we'd expect
pieces to weigh between 2t and 5t.
"At East Bay, California, it took seven years to get the
documentation done before we got the start on a similar job. The
original Avonmouth Bridge contract was changed to a partnership
form of working because of a lack of detail in the documentation.
There was a lot you couldn't see - you had to assume things that
didn't turn out right.
"We've done three times as much work as originally envisaged. It's
not a blow-out in cost as the rates to do the work are set. People
travelling over the bridge in cars think of it as a disaster, but
in fact it's an engineering triumph and the guys on site deserve
credit. The taxpayer has got good value for money."
With Cleveland Bridge's element of the contract now complete and
the painting contractors ready to undertake the final element of
the upgrade, the scheme will finally be done by the summer of 2001,
Rae calculated.