Arguments upon the jurisdiction of an adjudicator continue to cause
difficulty. I have reported through this column a number of cases
where the question of jurisdiction has been examined.
In Project Consultancy Group -v- The Trustees of the Gray Trust it
was held that failure to establish on clear evidence the existence
of a contract within the meaning of the Construction Act would deny
a party the means of conferring the necessary jurisdiction upon an
adjudicator. The judge held that an adjudicator could not, simply
by issuing his decision, create jurisdiction where none existed in
the absence of clear agreement between the parties.
In Palmers -v- ABB Power Construction Ltd the Court held that when
matters of jurisdiction were raised it was clearly appropriate for
the Court to intervene, since only when the Court had declared that
the relevant contract was a construction contract within the
meaning of the Act would an effective adjudication be possible.
This was particularly so given that there was no statutory power
available to an adjudicator if appointed to resolve disputes about
his jurisdiction. In Fastrack Contractors -v- Morrison Construction
the Court was asked to examine the question of whether a
pre-existing dispute was necessary to confer jurisdiction upon an
adjudicator. It was commented that a dispute could only arise once
the subject matter of the claim, issue or other matter had been
brought to the attention of the opposing party and that party had
had an opportunity of considering and admitting, modifying or
rejecting the claim or assertion. It was recognised that a genuine
jurisdictional challenge would occur when it was contented that
there was no dispute at all, where for example the whole of the
subject matter of the proposed adjudication had not been claimed,
notified or rejected. In Latham Construction -v- Cross the Court
held that an adjudicator lacked jurisdiction when he had looked
into the terms of a settlement agreement between the parties. That
agreement, although arising under the contract, was not of itself a
construction contract within the meaning of the Act. In Atlas
Ceiling & Partition Company -v- Crowngate Estates the Court was
prepared to take the question of jurisdiction one step further. The
judge ordered that the Summary Judgment Application for enforcement
of the adjudicator's decision be transformed into a trial of the
issue of the adjudicators' jurisdiction in open court, including
cross examination of the parties' witnesses. Having heard the
evidence, the judge held that the adjudicator had the necessary
jurisdiction and ordered that judgment be given for the sum found
by the adjudicator to be due.
This decision endorsed the correctness of the approach of many
adjudicators when faced with a challenge to their jurisdiction. The
adjudicator will be expected to investigate the contentions being
made and if in his view the challenge is unjustified, he will
proceed with the adjudication. This leaves the parties free to
continue their challenge to the jurisdiction if they so wish.
A further case which looked into the options available in respect
of a contested adjudication was the case of Workplace Technologies
Plc -v- E Squared Limited heard on 16 February 2000. The parties
were a trade contractor and sub-contractor for a building
management system to be installed at the Bluewater Shopping Centre
in Kent. Adjudication was started but a dispute arose between the
parties as to the date when the contract was entered into.
The adjudicator continued to deal with the substantive disputes
between the parties. Meanwhile, Workplace made it clear that it
disputed the jurisdiction of the adjudicator and its participation
in the process of adjudication was to protect its interest and
clearly under protest. Workplace was also making an application to
the Court for a declaration that the contract pre-dated the coming
into force of the Act and that the adjudicator had no jurisdiction
in the dispute between the parties. Moreover, it sought an order
restraining and preventing E Squared or the adjudicator from
continuing the reference to adjudication.
This latter request for an injunction to prevent the adjudication
from proceeding was in the event dropped by Workplace, but
nevertheless His Honour Judge David Wilcox QC considered it
appropriate to give guidance as to whether or not the Court would
have power to grant an injunction in such circumstances.
Judge Wilcox concluded that while an adjudication may proceed and
prove to be ultimately unenforceable, there is no clear legal or
equitable interest which required to be protected by such measures
as injunction. Doubtless the initiation of unenforceable
adjudication proceedings might be regarded to be a source of
harassment, pressure or needless expense, but this was not
considered sufficient for the Court to intervene.
In a situation where the existence of a relevant construction
contract is disputed, if the Court granted an injunction without
determining the question of the existence of the contract, then
would it follow that the Court might be interfering in a valid
adjudication to its detriment. The balance of convenience,
accordingly, favoured allowing the adjudication process to
continue.
BOXTEXT: INBRIEF
The Case: Workplace Technologies Plc -v- E Squared Limited, TCC, 16
February 2000.
The Issue: Whether the Court will order an injunction restraining
an adjudication pending resolution of a jurisdictional challenge.
The Implication: The Court will not grant an injunction to prevent
adjudication from continuing and thus jurisdiction will normally
only be challenged by way of defence to enforcement proceedings.