In February of last year I reported the case of Henry Boot
Construction -v- Alstom Combined Cycles which dealt with the
application of priced rates in bills of quantities to extended or
varied works.
The matter has now been decided by the Court of Appeal and by a
majority of two to one (which in itself shows how difficult these
matters can be), the Court has decided to affirm the earlier
decision of Judge Humphrey Lloyd QC.
Boot was engaged by Alstom under an ICE 6th Edition form of
contract to undertake main civil works including steelwork and
cladding for the Connah's Quay Combined Cycle Power Plant to be
located in Clwyd, Wales. Pre-contract negotiations included a
requirement to lower the excavations by a further metre within two
areas of the project around the turbine hall and in the location of
the heat recovery steam generator. The work involved the addition
of sheet piling to the excavations and Boot submitted a lump sum
price of £250,880 which it erroneously described as relating
to the work in the turbine hall only. This price had, however, been
calculated with reference to the quantities of both areas of the
building.
Subsequent to contract it was discovered that the sheet piling
would be required in a more extensive area around the cooling
towers. Whether a rate derived from the lump sum price for the
turbine hall could be applied to the full extent of the sheet
piling work became the subject of a dispute. The matter progressed
to arbitration.
The arbitrator refused to apply a rate extracted from the lump sum
price, firstly because of the difficulty of extraction and,
secondly, because he regarded the lump sum price to be mistaken and
he thought it unreasonable to enlarge the ambit of that mistake.
The dispute centred upon the well-recognised rules for the
valuation of variations which are contained in many standard form
construction contracts. In this case the ICE 6th Edition clause 52
(1) applied. For convenience the court broke that clause down into
three so-called rules.
Rule 1 a) Where work is of similar character and executed under
similar conditions to work priced in the Bill of Quantities it
shall be valued at such rates and prices contained therein as may
be applicable.
Rule 2 b) Where work is not of a similar character or is not
executed under similar conditions or is ordered during the Defects
Correction Period the rates and prices in the Bill of Quantities
shall be used as the basis for valuation so far as may be
reasonable.
Rule 3 Failing which a fair valuation shall be made.
Accordingly the term "reasonable" in Clause 52 (1) (b) required
examination. Judge Humphrey Lloyd QC had held in the Technology and
Construction Court that the reasonableness of the rate for the
purposes of Clause 52 (1) (b) was to be gauged strictly by
reference to the work carried out. It was inappropriate to take
into account extraneous considerations such as how a rate or price
was arrived at and whether it was too high or too low.
Judge Lloyd held that the parties had agreed that such a rate or
price was to be used to value variations. "The basic consideration
is that the contractor has agreed to do all work within the
contract, original and varied, on the basis of his bill rates".
Lord Lloyd (no relation to Judge Humphrey Lloyd) in the Court of
Appeal agreed with this proposition. He considered that Rule 2
provides a half-way house between rule 1 and rule 3, and is
mandatory. It applies when the work covered by the variation order
is of a different character from work priced in the Bill of
Quantities, or is executed under different conditions. If the
differences are relatively small the engineer is obliged to use the
rates set out in the Bill of Quantities as the basis for his
valuation. Only if the differences are greater is the engineer
entitled to take the view that it would not be reasonable to base
his valuation on the rates contained in the Bill of Quantities. The
engineer is then thrown back on rule 3 (fair valuation).
Lord Lloyd concluded that the words "so far as may be reasonable"
in rule 2 call for a comparison between the work covered by the
variation order and the work priced in the Bill of Quantities. They
do not enable the engineer to open up or disregard the rates on the
grounds that they were inserted by mistake.
Lord Justice Beldam agreed with Lord Lloyd. "It is the
reasonableness of using the rates and prices, and not the
reasonableness of the prices or rates, which has to be
considered".
Lord Justice Ward, however, in a dissenting judgement, was clearly
unhappy that such an analysis might lead to a substantial windfall
for the contractor. He could not accept that in applying clause 52
(1) (b) the engineer is not entitled to take into account the end
result of using the contract price, in judging whether or not that
use was reasonable or unreasonable.
In his earlier decision Judge Lloyd had found no difficulty in the
fact that the rates to be applied to the varied work were not
individually itemised rates, but were instead to be derived from
the intermediate step of extraction from within a lump sum for part
of the work. The Court of Appeal agreed that such concerns did not
affect the proper interpretation to be placed on clause 52 (1) (b)
and the matter was therefore to be remitted back to the arbitrator
to investigate in carrying out his valuation under rule 2.
BOXTEXT: INBRIEF
The Case: Henry Boot Construction Limited -v- Alstom Combined
Cycles Limited, CA, 4 April 2000
The Issue: Application of under or over-priced rates in Bills of
Quantities to extended or varied works.
The Implication: In assessing the reasonableness of a rate or price
in contract bills for extended or varied work regard may be had to
whether the work is similar in character or condition but not to
the intrinsic profitability or otherwise of the rate or price.