Exclusive by John d'Arcy
A shock ruling by a Liverpool court upholding a "heads we win,
tails you lose" disputes clause in a construction contract has
brought dismay to subcontractors and cast doubt on the future of
adjudication.
"This is a very serious development," said Rudi Klein, chief
executive of the Constructors Liaison Group. "It is horrendous news
for adjudication."
The case was heard by Judge Mackay at Liverpool's technology and
construction court. It involved adjudication proceedings brought by
subcontractors Bridgeway Construction against main contractors
Tolent Construction. The former were seeking the recovery of monies
that they claimed were due.
Klein said the substance of the court ruling was to uphold a
contract clause dictating that the party referring a dispute to
adjudication would have to pay both sides' costs irrespective of
the eventual findings. In this case, the adjudicator did indeed
find in favour of Bridgeway. The subcontractor still had to pay
both its own and Tolent's costs.
The subcontract was on the main contractor's standard terms which
incorporated the model CIC adjudication procedures - but with
amended terms regarding costs.
Klein contended that the outcome made a nonsense of the
adjudication process.
Bridgeway was represented by David Oram, of solicitors Hill
Dickinson. He said: "So far adjudication has proved a successful
method of extracting money from a recalcitrant payer since its
enactment under the Housing Grants, Construction and Regeneration
Act 1996. Coupled with the success of adjudication there have been
numerous attempts to draft adjudication terms that frustrate
adjudication as envisaged by the Act."
Oram said the court upheld terms within the contractual
adjudication procedure which provided that:
l The party serving notice of adjudication will bear all costs and
expenses incurred by both parties; and
l Shall bear all the costs of the adjudicators.
He continued: "On the law as it presently stands, it will be no
surprise if similar terms now become widespread in construction
contracts. And this should be a major concern for anyone wishing to
commence an adjudication."
Judge Mackay stated: "It seems to me that main contractors and
subcontractors are entitled to develop contracts to implement Acts
of Parliament. There are good grounds for saying that a system for
costs is important and relevant.
"The mere fact that in a particular case the claimants are
disgruntled, perhaps understandably so, about their costs situation
does not entitle me to say: 'Well, these clauses are a bit unfair,
let's change them.'"