It has often been said that, faced with an impossibly difficult and
complex dispute to resolve in too short a timescale, an adjudicator
might declare that the dispute was "non-adjudicable".
Quite what the effect of such a declaration might be is uncertain.
If it were to amount to a decision on the matters put to the
adjudicator, then the parties would be bound by that decision and
would not be free to commence a second adjudication or series of
adjudications, perhaps in a more ordered and manageable
fashion.
This question was examined in the recent case between Ballast -v-
The Burrell Company (Construction Management) Limited. Ballast was
engaged as management contractor, under a standard JCT form of
management contract, for the construction of a project in Glasgow
known as Homes for the Future.
The matters Ballast referred to adjudication involved the entirety
of its account. "The adjudicator is asked to assess the value of
work done, the common services, the management fee, loss and
expenses and other appropriate amounts due and payable and to make
directions as to the amounts due and payable to works package
contractors."
The adjudicator's decision in respect of the matters referred was
an enigmatic "not-valid". As far as could be determined from the
adjudicator's decision, he had been concerned to note that the
works packages had been placed using a bespoke form of contract
rather than the standard form envisaged by the JCT contract.
Other issues which had troubled him included that work had been
carried out without the issue of a formal architect's instruction,
but which, according to Ballast, had been informally instructed or
approved.
Despite these matters being a common feature of building contract
disputes, raising issues with which any practitioner would be
expected to be familiar, it appears that the adjudicator formed a
view that these problems rendered the dispute incapable of
determination by adjudication.
In his reasons the adjudicator noted "where the parties have
departed from a strict pre-agreed code then they have to accept
that it is, as with the courts, not the adjudicator's place to make
decisionsÉ".
Ballast's concern was that following the scheme, it might be
prohibited from commencing a second adjudication in respect of the
disputed accounts. Clause 9 (2) of the scheme provides that "an
adjudicator must resign where the dispute is the same or
substantially the same as one which has previously been referred to
adjudication and a decision has been taken in that
adjudication".
Ballast argued that the adjudicator was under a duty to decide the
matters in dispute. He had failed to do so. He was not entitled to
decide that he was unable to decide. It would be absurd if an
adjudicator could decide that he had too little information to make
a determination, thereby preventing the bringing of a second
adjudication if additional information became available.
The Court was requested to grant a declaration that the adjudicator
had failed to make any decision in respect of the matters referred,
and to set aside the adjudicator's decision as a whole.
Burrell, on the other hand, argued that the adjudicator had
implemented his duty under the scheme. He could validly decide that
he was unable to exercise his statutory jurisdiction. If the
adjudicator had taken the view, rightly or wrongly, that he was
empowered only to reach a valuation in accordance with the strict
terms of the JCT contract, that was an error falling within his
jurisdiction and with which the courts could not interfere.
Lord Reed reviewed the decisions of the courts dealing with the
setting aside of adjudicators' decisions on the question of
jurisdiction. The relevant cases have until now tended to the view
that an adjudicator's decision given properly within his
jurisdiction will be enforced whether that decision is right or
wrong.
Lord Reed commented, however, that it did not necessarily follow
that adjudicators' decisions were intended to be entirely immune
from challenge. He noted that he would be slow to attribute to the
parties an intention that the adjudicator's decision should always
be binding, notwithstanding errors of law, procedural unfairness or
lack of consideration of relevant material submitted to him by the
parties, no matter how fundamental such a breach of the
adjudicator's obligation might be.
So far as Lord Reed could make sense of what the adjudicator had
written, he appeared to have decided that he could not carry out
any valuation or find any payment due because the parties had
departed from the terms of the pre-printed contract in a number of
respects. Such an approach was wrong in law. As a result of that
error the adjudicator had misconstrued his powers and in
consequence failed to exercise his jurisdiction to determine the
dispute. His decision was therefore a nullity, leaving the parties
free to commence a further adjudication in respect of part or all
of the disputed matters previously referred.
Unfortunately there appears to be a lack of consistency in the
decisions of the courts upon how to categorise adjudicators'
errors. In SL Timbers -v- Carillion (CJ 11 July 2001), the
adjudicator refused to value the works as referred to him in the
mistaken belief that the absence of a S110(2) payment notice
prevented him from making such a valuation. In contrast to the
present case, the court treated this error as one with which it
could not interfere. This lack of consistency will trouble
adjudicators, who may detect a general drift towards more court
intervention.