Payment disputes involving a failure to provide a valid withholding
notice under the terms of the Construction Act are now more likely
to go to court than adjudication.
This is the conclusion of Liverpool solicitor Hill Dickinson
following a decision in the Salford Technology and Construction
Court.
Alan Pugh, a solicitor in the firm's construction department, said:
"In light of the judgment, parties who claim an entitlement to
payment due to a failure to provide a valid withholding notice may
well prefer to commence court proceedings rather than proceed to an
adjudication, given the availability of cost orders and statutory
interest."
The Salford court ruled that, irrespective of whether the defendant
had justifiable reason for withholding monies, the claimant was
entitled to summary judgement requiring payment on the grounds that
there was no withholding notice.
Rudi Klein, chief executive of the Constructors Liaison Group, said
the Salford decision was in line with a similar ruling by the
Chancery Division of the High Court. He added: "The courts are
firing a warning shot across the bows of non-payers. You fail to
issue a withholding notice giving reasons for non-payment at your
peril. Many people in the industry still seem to think the Act does
not apply to them. Either that or they are just ignorant of the
Act."
In the Salford case, subcontractor Millers Specialist Joinery
Company commenced proceedings and issued an application for summary
judgment on the basis of 10 unpaid invoices submitted for work
carried out at the Triangle, Manchester.
Judge Gilliland QC considered the application both on its merits
and in the light of the client's failure to provide valid
withholding notices. In the first instance he found the claim would
have failed "because it cannot be said that the defendant did not
have a reasonable prospect of establishing that it had a valid
counter-claim which under the general law it could rely on as an
equitable set-off".
However, summary judgement was awarded on the grounds that no valid
withholding notice was given under Section 111 of the Construction
Act.
The judge stated: "The effect of Section 111 is to prevent the
paying party, if it does not give appropriate notice, from
exercising his right to retain or withhold payment of monies which
would otherwise be due and payable but for the existence of some
right to withhold payment. Section 111 refers to withholding
payment generally.
"It must have been intended to include situations where the paying
party was legitimately entitled under the general law under the
terms of the contract to withhold monies which were otherwise
payable."
David Oram, a partner in the Hill Dickinson construction team,
concluded: "In view of this decision, there may be a marked
increase in the number of such disputes proceeding immediately to
court and a likely decrease in adjudications."