Exclusive by Carol Millett
The Highways Agency's (HA) and the Scottish Executive's decision to
pre-empt a European Commission directive to increase the number of
bidders on their design and build (d&b) contracts from four to
five goes against the Latham Report.
That is the opinion of the Civil Engineering Contractors
Association (CECA).
A recent European Court of Justice ruling calls for no less than
five bidders on any restricted procedure contract. The Commission
is now planning to include the ruling in the European procurement
directive early next year.
CECA director Rosemary Beales told CJ bid costs for design and
build road contracts will soar if the ruling becomes law. "This
ruling contradicts the UK's current good practice guidelines on
tendering. Five bidders are just too many on d&b
contracts."
The HA has already called for five bidders on the A5 Nescliffe
bypass and the A10 Wadesmill bypass. The Scottish Executive has
also called for five bidders for a d&b contract on the A1 near
Edinburgh. Beales said: "Some [clients] believe the ruling is
already law, but it isn't and we are hoping to prevent it being
applied to design and construct contracts before the procurement
directive is enacted next year."
Steve Rowsell, procurement director at the HA, confirmed that it is
following the ruling. He said: "With the high cost of tendering for
d&b, it is not satisfactory to use a minimum of five bidders,
but that is the ruling and that is what we are following for the
time being. However, we are moving away from traditional d&b to
early d&b contracts where there is less need for substantial
design work during the tender period, so it might be appropriate to
have five bidders on these sorts of contracts anyway."
But Beales queried Rowsell's logic. "I can't see how five bidders
on any d&b contract is wise. The number recommended by the
Latham Report is four."