What is the "withholding of a sum due" under a construction
contract? Put another way, when is it necessary to serve a
withholding notice in accordance with the Construction Act? This
question has troubled the industry since the Act came into force.
Thankfully the matter has been carefully examined on a number of
occasions by the courts and it seems a clear answer is
emerging.
One of the clearest comments came from Lord Macfadyen in the case
of SL Timber Systems -v- Carillion Construction in June 2001, where
he said: "I would have been inclined to say that a dispute about
whether the work had been done, or about whether it was properly
measured or valued, or about whether some other event on which a
contractual liability to make payment depended had occurred, went
to the question of whether the sum claimed was due under the
contract, therefore did not involve an attempt to 'withhold a sum
due under the contract', and therefore did not require the giving
of a notice of intention to withhold payment."
The conclusion to be drawn from this and other cases appears to be
that where the paying party disputes the amount properly due under
the contract, there will be no requirement to serve a withholding
notice. Nothing is being withheld. That principle would apply,
regardless of whether the paying party was simply relying upon a
contractual term for payments only to be made in respect of work
properly carried out, or was relying upon a general right of
abatement to take into account, for example, defective work.
Where however, the paying party seeks to resist payment by raising
a counterclaim to be applied as a set-off against monies otherwise
due (such as, for example, to deduct damages for delay in carrying
out the work), then a notice of withholding will be required.
This interpretation appears to be perfectly straightforward, but it
is in the nature of construction law that fringe arguments will
always be found which will create further difficulty.
An example is to be found in the case of Clark Contracts -v- The
Burrell Co (Construction Management). Clark was employed by Burrell
as contractor for the redevelopment of eight flats in Glasgow under
the JCT Standard Form.
An architect's interim payment certificate had been issued in the
gross amount of approximately £450,000, which after deduction
of retention and previous payments left a payment due of
approximately £30,000. Burrell refused to pay and Clark
commenced proceedings for the unpaid sum.
In placing its case before the court, Clark did not specify the
works which it had performed and which underpinned its claim for
payment. It simply relied upon the issue of the interim payment
certificate by the architect.
Burrell disagreed with the amount certified by the architect and
contended to the court that the amount stated as payable in the
interim certificate was not necessarily the 'amount due' under the
contract. By reference to clause 30.2 of the JCT Form, Burrell
argued that the sum due under the contract derived from the gross
valuation, which was defined to include the total value of the
works properly executed by the contractor.
In order to arrive at this figure, the work carried out had to be
assessed and valued in accordance with the Bill of Quantities.
Thereafter, the architect would issue an interim certificate. What
was therefore due was not necessarily what the architect said was
due. The architect's view, said Burrell, was indicative only and
not authoritative. The architect might get his assessment wrong and
his view was not therefore binding.
Behind this argument lay the fact that Burrell had not given a
notice of intention to withhold payment in accordance with the
Construction Act. Burrell maintained that it was not necessary for
it to do so, since Clark was not suing for a sum due under the
contract. The amount brought out as payable in the interim
certificate and the sum due under the contract were not necessarily
the same thing. Burrell concluded in its argument that the absence
of a withholding notice did not relieve Clark from the ordinary
burden of showing that it was entitled under the contract to
receive payment of the sum contended for.
Clark argued that this was wrong. In the absence of a notice of
withholding, Clark argued it had established an entitlement to
payment by reference to the architect's interim certificate.
It was not necessary to set out all of the contractual works that
it had performed in the course of the contract. This would be
farcical and would render the certification provisions of the
contract redundant.
The court preferred Clark's argument. The SL Timber case had not
concerned an architect's certificate, but simply a claim for
payment by the subcontractor. In this case, Clark became entitled
to payment of the sum stated in the interim certificate within 14
days of it being issued. That was an entitlement to payment of a
sum due under the contract. Thus, if Burrell wished to avoid a
liability to make such payment because the works did not conform to
the contractual standard, or because it disputed the certification
made by the architect, it would be withholding payment of a sum due
under the contract. Burrell would thus be required to give a
withholding notice in accordance with Section 111 of the
Construction Act.