If there is one thing a demolition company needs to be when it
comes to the decommissioning of a nuclear plant, it is controlled.
So it comes as no surprise that the demolition contractor working
closely with British Nuclear Fuels Ltd (BNFL) is none other than
the Yorkshire-based Controlled Demolition Group.
Nor is the association between the two companies something
new.
"The relationship has evolved over a period of six to seven years,"
says CDG managing director Darren Palin. "In 1995 BNFL invited us
to undertake the dismantling of reactor buildings at Berkeley near
Bristol and we haven't looked back since."
CDG was the first demolition contractor to undertake the
dismantling of reactor buildings at a UK nuclear power station and,
since then, the company has maintained its preferred contractor
status through a series of contracts within the nuclear power
station industry at plants such as Dounreay, Hunterston and
Aldermaston.
At the moment it is the Trawsfynydd nuclear power plant in north
Wales that is supplying the team with the most decommissioning work
and, according to Palin, it is thanks to the demolition industry's
preoccupation with safety that the company was able to help the
nuclear power station improve its poor safety record.
"Although demolition was by virtue of the name a dirty word when we
first started, we helped Trawsfynydd climb up the BNFL safety
league table," recalls Palin. "When we arrived, it was bottom of
the league."
Stringent risk assessment
Accustomed to working to strict safety requirements, CDG used its
extensive knowledge of stringent risk assessment to good effect.
"The nuclear inspectorate polices the sites heavily. If you drop a
spanner and that is not included in the method statement, it is
classed as an accident," says Palin. "For BNFL, safety is life and
death in real terms."
Fortunately the contractor has confidence in the client's
commitment to safety. "It practices what it preaches," he
adds.
By taking on an ex-BNFL engineer who had worked on the Trawsfynydd
site for 25 years, CDG was able to refine its method statements and
risk assessments. "The engineer worked in tandem with our project
manager and stayed with us for two years before retiring," recalls
Palin.
In March 2001, the demolition contractor also established a
research working party with BNFL to look at ways of improving
methods of deplanting nuclear reactor works and, in particular, the
development of machinery capable of tackling reactor ponds and
pools.
Despite the need for such stringent safety measures, CDG has not
been slow to recognise that decommissioning work in the nuclear
power plant industry will provide rich pickings for the demolition
contractor.
"There will be 15 nuclear power stations coming off line," observes
Palin, before commenting that each project presents a different
challenge.
"We are trying different ways of dismantling power stations so that
they can be reused as brownfield sites - mostly for industrial
purposes."
The initial contract at Trawfynydd involved a 40-week deplanting
project. This comprised the removal of steam and ancillary
pipework, steam vessels and other equipment from the reactor's
boiler house.
Along with demolishing the boiler head, CDG has dealt with the
dismantling of the incinerator building, boron dust building and
turbines.
The latest contract for BNFL has been the decommissioning of the
main turbine hall at Trawsfynydd in a project worth £1.7m to
the demolition contractor.
Built in 1961, the bombproof turbine hall is described as being of
colossal proportions - a mainly steel-framed building with both
precast concrete and pressed metal deck cladding, it is 110m long,
72m wide and 34m high at its tallest point.
Although CDG is probably best known for its explosive work,
traditional demolition techniques were used when work started in
September last year.
As the contents of the turbine hall was contaminated by both oil
and radioactive particles, the demolition team used hot cutting
techniques to dismantle equipment piece by piece while maintaining
stringent safety precautions .
"Once the components have been tested for radiation levels,
everything is recycled," explains Palin. "The 18,500t of rubble
from the demolition will be crushed for use as backfill and 10,000t
of steel will be recycled on site."
The contract also included a complex four-week operation where
asbestos contaminated concrete panels had to be dismantled.
About 100 risk assessments were carried out in the turbine hall
alone, but apparently that was only the beginning, since careful
monitoring continues throughout the project.
One of the largest boxes in the world
According to Palin, this has left the site with what he describes
as one the "largest boxes in the world" with 5m to 6m-thick
reinforced concrete bases.
"We had to hand demolish the contents piece by piece as the gable
end was connected to an adjoining single-floor office block
attached to the back wall of the turbine hall."
Added to which, the turbine hall is less than 100m from the now
redundant reactor hall.
After a short break in which BNFL was able to reroute mains
services away from the hall, the CDG team has now returned with a
state-of-the-art Komatsu PC750 ultra-high-reach machine with a
40m-high operating capability to begin demolition of the main
structure and its 45cm thick fireproof walls.
The project also includes the dismantling of three concrete water
tanks in the hall roof plus 12 transformer loading bays leading
from the main building. "We expected the project to take 54 weeks
to complete, but using our ultra-high-reach and high-reach
excavators, we anticipate completion within 46 weeks," says
Palin.
When asked why there is such a sense of urgency to decommission so
many nuclear power stations, Palin says: "A lot of them are 30 to
40 years old," explains Palin. "They were only designed for 25
years. However, when the North Sea oil reserves are depleted, what
alternative is there? At best, the green alternative can only
supply 20% of the national requirement."
With so much nuclear power station decommissioning work in the
offing, CDG is re-considering its programme. "We are now reviewing
our strategy for the future," says Palin. "As a company, we have
expanded and we are still expanding. Instead of one division, we
will operate from four divisions. These are: traditional
demolition; decommissioning; explosives; and asbestos."
As well as decommissioning nuclear power plants, CDG is also
looking at the oil industry where 200 major oil platforms have
exceeded their economic life.
"They are being brought to land for dismantling and our skills
could be translated into that sector," says Palin. n