It is not often that I will get the opportunity to report a case
from the Falkland Islands Supreme Court, but the case of Attorney
General for the Falkland Islands -v- Gordon Forbes Construction
deals with a point of general interest in the management of
claims.
Forbes had entered into a contract with the Falkland Islands
government for the construction of the infrastructure of the East
Stanley Housing Development in the Falkland Islands. The contract
was based upon the FIDIC Conditions of Contract for Works of Civil
Engineering Construction, 4th Edition.
Disputes arose between the parties and these were referred to
arbitration. During the course of arbitration an issue arose as to
the meaning of clause 53 of the FIDIC Conditions. Clause 53 sets
out a procedure which the contractor must follow in the event that
he intends to make a claim. This clause is reflected in the more
recent editions of the FIDIC forms of contract and is also to be
found in many other standard forms including the ICE 7th
Edition.
Briefly, Clause 53 requires that if the contractor intends to claim
any additional payment under the contract, he is required to give
notice of his intention to the engineer within 28 days of the event
giving rise to the claim.
The contractor is then duty bound to keep such contemporary records
as may reasonably be necessary to support any claim he subsequently
makes.
The engineer is given rights to inspect those records and to call
for further contemporary records. The contractor is then to send
the engineer an account giving detailed particulars of the amount
claimed and the grounds upon which the claim is based.
Clause 53(4) concludes by saying that if the contractor fails to
comply with any of these provisions, his entitlement to payment is
restricted to such amounts as the engineer assesses the claim to be
worth based upon whatever contemporary records are available.
Purpose of clauses
The entire purpose of clauses such as FIDIC Clause 53 is to provide
a disciplined way of dealing with claims for additional payment.
Claims have to be notified at the time they arise and contemporary
records have to be kept and regular accounts rendered.
The whole contractual system is aimed at the early resolution of
any queries at the time the claim arises, with the likelihood that
plant, manpower and witnesses are still on site.
The obligations of Clause 53 fall almost entirely on the shoulders
of the contractor and the wording of the contract is mandatory
Ð the contractor ÒshallÓ do these things. The
essential substance of such clauses is, therefore, that if there is
no contemporary record to support the claim, the claim fails.
Unsurprisingly, both the Falkland Islands government and Forbes
Construction agreed this interpretation.
Forbes was keen, however, that the court should agree with a
clarification. It wanted to produce witness statements which would
help to fill in the gaps in any situation where there was a
shortfall in the contemporary records.
Before answering that question, Judge Sanders felt it appropriate
to clarify what was meant by the term Òcontemporary
recordÓ. The term is not defined in FIDIC and it has not been
the subject of judicial guidance previously.
Judge Sanders concluded the contemporary records meant original or
primary documents or copies thereof, produced or prepared at or
about the time giving rise to the claim, whether by or for the
contractor or employer.
The making of the record does not have to be instant, and whether
or not a record was to be regarded as contemporary would depend on
the facts surrounding the making of that record. It would, however,
be exceptional if any record could be regarded as contemporary if
made more than a few weeks after the event.
Judge Sanders concluded that it would be perverse if a contractor
who had failed to comply with the terms of the contract should then
be allowed to produce non-contemporary records to support a claim,
particularly as these could not properly be investigated by the
employer at a later date.
The rights of the employer to inspect the records at the time the
claim arose were fundamental to the FIDIC procedure.
This fairly strict interpretation leaves little room for
contractors to manoeuvre. The requirement to keep good records of
activities on site in the event of a claim remains paramount. Judge
Sanders confirmed that there are, however, exceptions where witness
statements may be brought into play.
If contemporary records are in some way ambiguous or unclear, it
would be acceptable for the tribunal to take into account witness
statements which seek to resolve that ambiguity or lack of
clarity.
Judge Sanders also commented that a valid claim might exist,
despite the absence of direct contemporary records, where
inferences could be drawn from the existing contemporary records to
show that otherwise unsupported parts of a claim were valid.
An example of this would be where the contractor claimed four weeks
work by labourers, but the available contemporary records only
supported a claim for weeks one, two and four.
It may be reasonable for the tribunal to infer from these records
that the contractor continued to provide work for all four weeks
and witness statements may be admitted in support of that
contention. The tribunal would need to bear in mind however that
the burden of proof in all such matters rested with the contractor.