When your client tells you that it will lose £1.5m worth of
business if the contract you have been working on for more than a
year is not completed on time, then you know the pressure is
on.
That is the position Shepherd Construction finds itself in as it
enters the final stages of a 62-week contract to design and build
an indoor/outdoor water park, a 216-bed Caribbean-themed hotel,
450-delegate gothic-themed conference centre and 300-seater
restaurant.
But as the deadline looms, any doubt that the 16,000m2 project will
not be completed on time are dismissed by construction manager
Steve Hudson.
He says: "We always knew that we had 62 weeks and that the deadline
was set in stone. It brought home to us how close we were to the
deadline when in April we saw adverts in Sunday newspaper magazines
stating that the water park at Alton Towers would be open to the
public on 1 June.
"Bookings worth £1.5m have already been made for the
conference facilities this summer. However, despite seeing the
dates in print I never once feared the project would not be
finished on time and to budget."
Shepherd is no stranger to working on theme parks; it has built
them in Blackpool and Southend. The contractor is also well known
to the Tussauds Group, which owns Alton Towers. It built an
identical hotel on the giant Staffordshire site seven years
ago.
Initially the latest contract was to build a hotel along the lines
of the original one, but then one of Alton Towers' main board
directors went to America, saw said water park and decided there
and then that he wanted Alton Towers to be the first theme park in
Europe to have one.
As a result, the project escalated from being a £12m hotel to
a £49m water park and the race to win the prestigious,
groundbreaking contract was on.
"The contract went to a two-stage tender and we were one of four
bidding," recalls Hudson. "We won the first stage tender, despite
not being the cheapest, after convincing the client that we could
do the job quicker than our main competitors. Originally it was a
72-week programme, but by changing the scope for the hotel from
traditional masonry to a pre-cast construction we were immediately
able to reduce it by 10 weeks.
"We then trimmed another six weeks off by looking at ways we could
design the steel frames through prefabrication."
The contractor's work on the original hotel in 1996 was also an
important factor as far as Tussauds was concerned.
"Shepherd had zero defects on the first project, while the one or
two minor problems we did have were dealt with immediately," says
Hudson.
"The original project was on time and to budget. We also used our
own architects and engineers on this project as part of an
identical package."
However, top of the agenda was safety. The client made it clear it
did not want any of the bad publicity that would be generated if
anyone was killed or seriously injured working at one of Britain's
most famous theme parks.
"Safety has always been the priority for us too," adds Hudson. "We
have a dedicated safety manager - he has no other responsibilities
apart from safety. He is in charge of making sure method statements
are in place, that the operatives have read its contents and are
aware of it, while he continually walks around site assessing
operations."
Although there appears to be no stumbling blocks in the
construction work itself, the location of Alton Towers caused three
huge problems.
"The first was us being unable to get any deliveries on site," says
Hudson. "With thousands of people arriving from 7am onwards in the
summer to avoid the queues and get on the rides first, it was a
nightmare.
"Second, the surrounding roads are so small that there is only one
route we can use to get the largest steel sections into site. We
had to come from Ashbourne down the A52 because it had the fewest
number of bends.
"Finally, throughout the winter, all boarding houses shut down
because Alton Towers was closed and there was no business.
"With 150 of my 300 staff lodging away from home we had to ring all
the locals to see if any were willing to open up. In fact we
actually encountered hostility from some boarding houses, with many
refusing point blank to have anything to do with us because we were
building another hotel and they saw that as a threat to
them."
However, once Shepherd's operatives were able to set foot on site
they could not fail but be impressed with the way the client just
left them to it.
According to Hudson: "It has been a real team effort from start to
finish. You cannot always achieve the client's aspirations from an
artists' sketch, so there has been a lot of open discussion.
However, Alton Towers realised that if it didn't leave us to it,
and kept wanting to tweak things here and there, we would never
finish the job."
Provided the completion date is secured, and as a token of its
appreciation, the client has offered a free holiday to every
operative on site.
"Every person who has contributed to the substantial effort made on
the project will get an overnight stay in a family room with one
day in the water park and access into the main theme park for a day
as well," says Hudson.
With many of the workers having been on site from 7am to 11pm in
two shifts, seven days a week, as the project peaks, and all leave
cancelled until deadline day, no one would argue that a short
holiday is the least they deserve. n