Rail contractors could enjoy substantial windfalls if they show
innovation when pricing up work packages under Network Rail's seven
new track renewal contracts.
Speaking exclusively to CJ, the rail operator's chief executive
John Armitt said negotiations are taking place to allow contractors
a generous gain and pain share on forthcoming regional work
packages, believed to be around 5% to 10%.
The exact details of the gain/pain share has still to be decided as
the renewals programme has only just reached preferred bidder
stage. However, initial signs indicate that contractors will be
able to make substantial gains on their bottom lines in a series of
packages ranging between £5m and £15m over the five-year
duration of the contracts.
The preferred bidders include Amey, Balfour Beatty, Carillion,
First Engineering and Jarvis (see box). Work on the new packages is
set to start in April next year.
"Contractors are pleased with the deal so far, although they didn't
want the gain and pain figures set too high and to be unrealistic,"
said Armitt. "The gain/pain share could be based on how a
contractor goes about planning its possessions with Network Rail
engineers, or how productive it can be when laying track or using
machinery."
However, Armitt hinted that contractors will be kept on their toes
as Network Rail will set different targets for contractors to
achieve on each round of work packages.
Network Rail will now sit down with the preferred bidders to thrash
out terms and will make an announcement before September.
Commenting on why the renewals awards were delayed, Armitt said:
"The decision took time as we were determined to get it right and
we still had 10 months left on the existing contracts."
However, one insider told CJ that Network Rail "stifled innovation"
during the procurement process and "just went for lowest
cost".
Armitt replied: "We have two stages in procurement. At first we
wanted an apple-for-apple comparison. We asked contractors to just
tell us what their price was for a basic job. This won't stop us
going back to the contractor for ideas on innovation in the second
stage."
* Additional costs and an urgent recruitment drive are the first
hurdles Network Rail will have to overcome having taken Amey's
£45m-a-year Reading contract back in-house.
"This is going to be a challenge, but it will work. It has to
work," new zone manager Brian Timms told CJ.
Amey's plant contracts will be maintained until March next year.
Some of Amey's 500 staff, who were transferred under TUPE rules,
have left the job, but Timms refused to confirm the exact
figure.
However, he is looking to employ 50 track workers.