Shoring up the Sow
Stafford might not be on everyone's tourist trail, but this doesn't
mean the town, made popular in Victorian times, is not an
attractive spot to visit. When visitors emerge from the railway
station, they face the appropriately named Victoria Park and should
they choose to get to the town centre on foot, they will cross a
footbridge over the River Sow and have a bird's eye view of flood
defence work currently being carried out by Jackson Civil
Engineering. The reason for this construction activity is the
serious flooding that occurred in Stafford in November 2000. This
wasn't the only occasion. The Victorian town has a history of
flooding with particularly bad instances occurring in 1946, 1977
and 1981.According to the Environment Agency (EA), an asset survey
carried out in 1994 concluded problems were developing at the river
edge in Victoria Park. This was attributed to poor ground
conditions in Stafford and the authorities decided that the
existing piling was in need of repair.As well as repairing the
retaining walls and flood defence wall protecting the town, the
project's aim is to upgrade the town's flood defences from a 1 in
25 year standard (see box for flood classification) to a 1 in 100
year standard.The project is divided into two phases with the first
phase carried out between April and October 2002. The second phase
is scheduled to follow a similar time frame this year. JCE is
engaged on a 3.6m contract to build new retaining walls to replace
the existing bank structures and to install 2,000 sheet piles along
part of the River Sow which flows through Stafford. According to
Paul Watson, JCE's project manager, an 1,800m stretch of the
riverbank is being strengthened with the flood defence wall
covering a length of 350m.The working area is at a premium for JCE
operatives as the riverbank allows little room for manoeuvrability.
"We have to clear areas immediately adjacent to the river so that
we can sheet pile," explains Watson.Due to the space constraints,
not helped by the canopy of trees along the riverbank, JCE opted
for a side-grip sheet piler.With its side grip, the sheet piler can
handle piles up to 13m-long and thanks to an on-board computer that
controls the verticality of the pile, it also reduces the need for
a piling guide.Because the ground is so soft, Watson says they did
not experience a period of high vibration.As one of the first full
contracts to operate under the EA's National Contractors Framework
Agreement, what are Watson's first impressions?His response is
positive."There is more interface between the designer, EA and
ourselves," he says. "It is a shared experience and if there are
problems in the offing, they are solved early on."Watson also
points to the fact that while there is less bureaucracy, there is a
mechanism within the framework that allows team members to
continually evaluate the way the system works."It is being looked
at closely by the people within the framework and where things can
be improved, there is the opportunity to do so. Frameworks are good
from a contractor's point of view as you can plan better and more
effectively."This is a sentiment echoed by James Mallender, EA's
project manager."There are already great examples on site of the
new framework principles being adopted showing team decisions on
the supply chain. Working closely together with JCE and EA
consultants, Atkins, means that as a unit we can be flexible,
reacting quickly to implement solutions for the day-to-day
challenges that arise on site."An example of incorporating clever
ideas at an early stage was Atkins' proposal to install a
reinforced earth section on the side of the riverbank. Designed to
be a storage area for the water between the river and the in situ
concrete flood defence wall in the event that the river water
levels rise, the reinforced earth section has a depth capacity of
600mm."The cost of installing piles was more than the procedure to
reinforce earth," recalls Watson. "It is a clever design and only
works in a location like this."Maintaining a high standard on the
project is one of the team's key objectives and Jim Chaplin, JCE's
key client/services director, says the contractor has a big
incentive to perform."Our performance is linked in with the EA's
objectives. These include environmental issues as well as health
and safety," says Chaplin.While he is clearly delighted that JCE
has become an EA framework contractor, he is under no illusion as
to what working in such an agreement entails."To get to the true
benefits, contractors must be involved at a much earlier stage.
Traditionally, we only get involved when the project has already
been designed so it is almost too late for us to contribute much.
Being part of a framework agreement enables us to be involved as
early as the feasibility stage."Does that mean JCE can afford to be
complacent about the agreement being renewed after the initial
five-year period is over?"There is absolutely no certainty it will
continue past five years," says Chaplin emphatically. "It is a
process of continuous development. Five years is no time at all and
it is unlikely that any significant work will be achieved in one
year where we will only see a shallow learning curve. We will only
see major benefits of working within the framework agreement in
four to five years' time."According to the EA's Mallender, the
framework team's performance is judged on a quarterly basis."We
hold an open meeting with the consultant and contractor and it is
an occasion from which we all learn a lot."Another body working
closely with JCE is Staffordshire Wildlife Trust."A wildlife
corridor is being created on site that will allow small mammals,
such as water voles to move along the river, as well as provide
refuges for fish and other water creatures," explains
Watson.Besides fish and water creatures, other local residents
include interested passers-by who stop to watch the work and --
given the opportunity - to have a chat with a JCE operative."There
is no restriction on the team speaking to town residents," says
Watson. "The company actively encourages operatives to communicate
with the locals. After all, if you're telling them the truth, you
have got nothing to hide."