Part of BAA's T5 core terminal is being built off site in a trial
run aimed at streamlining its final construction.
The trial run is part of BAA's wider policy of maximising off-site
assembly and pre-fabrication techniques on the T5 programme.
An integrated team of suppliers are pre-assembling the
façades and roof cassettes of the core terminal at a test
site at Severfield Rowan's yard near Thirsk, Yorkshire.
T5 construction director Andrew Wolstenholme told CJ: "A critical
element of achieving and delivering the T5 programme is in
maximising off-site assembly and prefabrication and in taking some
key elements off the critical path on site to ensure a smoother,
safer construction process with no surprises." He added: "This is
live, off-programme risk management."
The study involves building one full-scale end roof abutment
section, which is 30m long by 30m high. The trial run is expected
to be completed by September. The components will then be
transported to the T5 project ready to be rebuilt on site. The
study aims to resolve any unknown problems prior to assembly on
site, test the engineering principles, refine the temporary works
and improve safety.
The integrated team members are: Ove Arup; HOK; Rowan Structures;
Hathaway Roofing; Schmidlin UK; Laing O'Rourke; and Mace.
Wolstenholme said the additional cost of a trial run was more than
compensated by the learning curve. "There is a clear business case
for a trial run of the structure. The only elements we will lose
are the concrete piles, the overslabs and the man hours of the
erection team, but the lessons learnt are hugely valuable in order
to guarantee a clear production run."
Off-site manufacturing will feature large in the 3.7bn project in a
bid to keep down costs, reduce risks and limit the numbers of
workers on site at any one time. The bulk of materials will be
delivered by rail to the site's Coln Brook logistics centre, where
it will then be prefabricated or distributed to site using
just-in-time methods.
All concrete reinforcements will arrive by train and for the first
two years of the contract be prefabricated at the factory. Lead in
times for reinforced cages will be reduced from 10 days to two to
three days using this method. More than 70% of M&E components
will also be manufactured off-site.
Wolstenholme commented: "We expect to increase productive working
on site by 10% to 20% above the average 50% to 60% on a typical
site."