07:58 22 Aug 2003
|
The new Scottish Parliament building will
not be ready until July next year, presiding officer George Reid
confirmed yesterday (Thursday).
He made the admission in his latest
progress report to members of Holyrood's finance committee of a
project which is now rumoured to have reached the £400m
mark.
Reid told MSPs in his letter that the
latest delays would lead to an increase in the cost of the project
after main contractor Bovis Lend Lease told him that the projected
completion date had to be extended from November 2003 to July
2004.
However, Reid said that the recently agreed
cap on consultants' fees had saved £4.6m.
The biggest challenge of the project at the moment, said Reid, is the completion of the lightwell area - an access area with overhead glazing.
"Despite very considerable efforts to meet
the programme, it has proved impossible," he said.
"The key reason is that Drawn Metal, the
window contractor, has been unable to fit the windows quickly
enough, largely due to the additional blast proofing.
"The result of this is that Mero, the
specialist glazing contractor, cannot access the same lightwell
area to complete their works.These delays have a knock-on impact on
our ability to fit out the chamber and other critical works."