Final certificates have been a feature of most building and
engineering contracts for at least a century and a substantial case
law has developed primarily concerned with the nature and extent of
their evidential effect.
The intention of such certificates is to provide a means of finally
putting to rest the contractor's contractual obligations. They are
also intended to bring to an end disputes arising out of the
contract, particularly those concerned with valuation, with the
quality of the contractor's performance and with any delay in
carrying out the works. In consequence, a final certificate often
has a draconian effect on the rights of at least one of the parties
to the contract.
The requirements of a final certificate were discussed in the
recent case of Cantrell -v- Wright & Fuller. Cantrell owned and
operated a nursing home and had entered into a JCT 80 form of
contract with Wright for the construction of an extension to
provide an elderly mental institution unit. The works did not
progress smoothly and there were ongoing disputes concerning delay
and valuation.
By March 1999, more than one year after practical completion, those
disputes had still not been resolved. At that point however, the
architect issued a final valuation accompanied with a covering
letter that described the valuation as a final certificate. Usually
it would be the contractor that would object to such a step. In
this case however, it was the employer, Cantrell, that took
immediate exception to this valuation, arguing that it allowed
payment that it had no liability to pay.
Cantrell also objected that the works contained defects and that it
was entitled to liquidated damages for delay to completion.
Equally, Wright made known its views to the architect that there
were no such defects and that it was entitled to a full extension
of time.
Despite this, it was not until three years later that Cantrell
started arbitration proceedings. The significance of that was not
lost on the solicitor firm advising Wright. It drew attention to
the contractual provision that made the final certificate
conclusive evidence unless proceedings had been issued within 28
days of its issue.
In other words, the contract clearly stated that the final
certificate would provide conclusive evidence that all effect had
been given to the terms of the contract for adjustment of the
contract sum, extensions of time and reimbursement of loss and
expense.
The parties eventually found themselves in front of an arbitrator
seeking a decision as to whether the architect had validly issued a
final certificate. The arbitrator held that the document was a
valid final certificate and, unhappy with that ruling, Cantrell
appealed that decision to the court.
His Honour Judge Thornton considered the various complaints made by
Cantrell concerning the circumstances that led to the architect's
issue of the disputed final certificate. He noted that the final
certificate need not be issued on the standard template provided by
the JCT, but it must make it unambiguously clear that it is the
final certificate.
In addition, he considered the timing of the final certificate. In
his view, it may be necessary to allow a relaxation of the
prescribed timescales subject to the requirement of
reasonableness.
This meant that the form and content of the certificate issued by
the architect was not fatal to its validity as a final certificate,
and neither was its timing.
Judge Thornton turned his attention to the conditions precedent
that might apply to the issue of a final certificate. He noted that
there were a number of certificates or decisions required by the
architect that might be a condition precedent to the issue of a
valid final certificate.
First, Judge Thornton considered the certificate of making good
defects. In his opinion, the issue of a certificate of making good
defects was not a condition precedent to the issuing of the final
certificate, since it might never need to be issued at all.
However, where appropriate defects had been notified, such a
certificate would be required and, until it had been issued, no
final certificate could be issued.
Second, Judge Thornton considered the documentation that the
contractor was obliged to provide to the architect within six
months of practical completion for the purpose of the adjustment of
the contract sum and the corresponding obligation of the architect
or quantity surveyor to prepare a statement of adjustments within
three months thereafter. Judge Thornton concluded that the
architect retained authority to issue a final certificate even if
these documents had not been provided.
A further impediment to the final certificate would, however, be
where there was to be an adjustment to the contract sum of one or
more nominated subcontractors. Where such an adjustment had taken
place, the contract required a period of 28 days before a final
certificate could be issued. Thus, if a final certificate was
issued that included for the first time an adjusted amount in
respect of a nominated subcontractor, the final certificate would
be invalid.
Finally, Judge Thornton considered the questions of delay and
extension of time. It was clear in his mind that no final
certificate could be issued where practical completion had occurred
after the contractual completion date, unless a non-completion
certificate had been issued and the architect had concluded the
process of fixing or confirming the revised completion date. The
issue of these two certificates were condition precedent to the
issue of a valid final certificate.
Returning to the present case, neither the non-completion
certificate nor the final review of extension of time had been
issued by the architect. For those reasons in particular, Judge
Thornton concluded that the certificate issued in March 1999 was
not a valid final certificate. Cantrell was therefore entitled to
bring evidence of all other matters it contended should be
considered within the final account.