In September 2002, I reported the case of The Construction Centre
Group -v- The Highland Council. That case dealt with, among other
matters, whether an employer was able to raise a withholding notice
after the publication of an adjudicator's decision, to resist
enforcement of that decision.
In April of this year, that decision was the subject of an appeal
to the Inner House of the Court of Session in Scotland where
further detailed discussion on the rights of the parties took
place.
The Construction Centre Group had been engaged by the Highland
Council to undertake the design, construction and maintenance of
works involved in the Small Isles and Inverie Ferry Scheme on the
west coast of Scotland.
Disputes arose and these were referred to adjudication under the
HGCRA 1996. The adjudicator ordered the council to pay the
Construction Centre the sum of about £250,000.
The money was not paid and the parties ended up in the Court of
Session in Edinburgh. The Construction Centre sought enforcement of
the adjudicator's decision.
The council raised arguments to resist that enforcement. In
particular, the council complained it was entitled to apply a
deduction or set off for liquidated damages for delay, which it had
quantified in the amount of £420,000.
Within seven days of the adjudicator's decision, the council had
issued a Section 111 withholding notice in respect of those
liquidated damages.
The council argued that a withholding notice could not have been
issued prior to the adjudication because the engineer had issued a
'nil' valuation. Accordingly, there was no sum due under the
contract against which a withholding could be made. The council
maintained that now a sum had been awarded by the adjudicator, it
should not be deprived of its right to make such a deduction.
On hearing these matters at first instance in the Outer House of
the Court of Session, Lord Macfadyen made some surprising
comments.
First, he said the council had not needed a withholding notice to
argue in the adjudication that it had a right to apply liquidated
damages for delay against any sums which the adjudicator might
subsequently award.
Some would argue against that, on the basis that liquidated damages
do not concern the valuation of the work carried out, but instead
concern the separate grounds that an employer may have to apply a
cross claim or set off, flowing from the contractor's breach.
Setting those arguments aside, it was nevertheless the case that
the council had not raised by way of defence or cross claim its
entitlement to liquidated damages before the adjudicator. The
consequence, according to Lord Macfadyen, was that the council
could not later resist enforcement of the adjudicator's decision by
raising a Section 111 withholding notice after receipt of the
decision. Section 111 of the Act did not permit the giving of a
withholding notice in respect of an adjudicator's award.
That finding was examined by Lord Hamilton on appeal to the Inner
House. A further complication was that a receiver had been
appointed to the Construction Centre.
By clause 63(4) of the ICE conditions of contract, the council
argued that it would not be liable to pay the contractor any
further money until the end of the period of maintenance when the
costs of completion had been ascertained and certified by the
engineer.
The council elaborated that an order by the adjudicator for the
employer to make a money payment was no more than money "on account
of the contract" and where clause 63(4) applied, the obligation to
pay was suspended.
The Construction Centre disagreed. The case of Levolux
-v- Ferson Contractors in January this year was raised. There, the
Court of Appeal in England had held that where a conflict arose
between the obligation to pay an amount stated in an adjudicator's
decision and the prevailing contract terms between the parties, the
adjudicator's decision should take precedence. The Construction
Centre contended that, as a dispute resolution procedure,
adjudication was not simply a process of ascertainment of sums due
under the contract, such as certification by the engineer, but
involved a judgement, albeit provisional, on the parties' disputed
contentions.
If the adjudicator had been presented with a claim for liquidated
damages, he would have been entitled and bound to consider that
claim. The council had chosen not to put before the adjudicator its
claim for payment of any liquidated damages for delay and
completion. The Construction Centre said it would defeat the
purpose of the adjudication if the court were to entertain that
claim in enforcement proceedings.
In considering these arguments, Lord Hamilton was clear that the
process of interim certification was quite different from the
adjudication process. The issue of payment certificates did not
constitute the resolution of any pre-existing dispute and was
therefore quite distinct from adjudication. It made no difference
whether the claims now raised by the council were retention or
compensation (broadly equivalent to abatement and set-off in
English law).
It was sufficient to hold that, not having relied upon its claim
for liquidated damages as it might have done before the
adjudicator, the council could not now raise that claim in this
action for enforcement. That would not be consistent with its
contractual obligations to give effect to the adjudicator's
decision.
The appeal was dismissed and the Construction Centre was entitled
to enforcement of the adjudicator's decision for the payment of
£250,000.