The South Holland Centre in Spalding, Lincolnshire, is a theatre
and arts centre that puts on more than 100 shows a year, ranging
from dance and jazz to comedy and children's shows.
The centre has also been the back drop for a rather long running
dispute between the owner, South Holland District Council, and the
building contractor, Hallamshire Construction, which carried out
refurbishment works to the centre in 1997.
The contract between South Holland and Hallamshire was based on a
JCT 1980 Local Authorities version with Quantities. Hallamshire
complained that its work had been delayed and disrupted. It
submitted claims that were the subject of negotiation between
Hallamshire and South Holland's architect and QS.
Meanwhile, South Holland was impatient to press ahead with phase
two of the project for fit-out works, but was having difficulty
negotiating the scope and price for those works with
Hallamshire.
The parties decided to agree a way forward, such that the phase two
work would be instructed by means of a variation issued under the
existing contract. The relevant architect's instruction was duly
issued, instructing Hallamshire to complete the phase two fit-out
works in accordance with the bills of quantities, drawings and
specifications with the proviso that all costs in connection with
the variation were to be agreed as fair and reasonable costs by the
QS.
The architect's instruction also confirmed a revised completion
date to take account of these works, and, since negotiations had
obviously been proceeding well, noted that a full and final
settlement of the prolongation and disruption claims under phase
one had been achieved.
The fit-out works progressed to completion but the negotiations
concerning the price stalled. Eventually these disputes were
referred to arbitration and, after the arbitrator had delivered his
award, the case was referred on appeal to the High Court.
The statutory provisions that govern arbitration in the UK dictate
that there can be no appeal upon any finding of fact by an
arbitrator. Subject to the leave of the court or the agreement of
the parties, appeals can only be raised if there is a question of
law affecting the arbitrator's decision.
In bringing the arbitration, Hallamshire contended that the phase
two work had been undertaken without any contract. To determine
whether a contract had been formed for the phase two works, one had
to look to the usual contractual formation mechanisms recognised by
English law, namely an unqualified acceptance of an offer covering
all of the terms necessary to create a contract. The architect's
instruction was not an offer capable of acceptance because it was
lacking essential terms, notably the price for the work. All the
instruction really did was to identify the process for agreeing the
price. In other words, it was an agreement to agree, which would
not be recognised as contractually enforceable in English law.
The upshot of all of this, according to Hallamshire, was that the
arbitrator should have ignored the various rates and prices in
bills of quantities that had been exchanged between the parties in
attempting to agree a price. Instead Hallamshire should be paid a
reasonable cost plus profit for performing the work in the
conditions actually encountered.
South Holland approached the matter from an entirely different
stand point, arguing that no separate contract was ever necessary
or intended in respect of the phase two works. The architect's
instruction took effect as an instruction for a variation issued
under the original contract, and thus the phase two works
constituted extra or additional work to be performed under that
original contract.
The remuneration to be paid was defined by the architect's
instruction and to the extent that any rates or prices remained
unagreed, the parties would need to fall back on the contractual
machinery provided by the original contract with the architect
having the right unilaterally to fix rates and, in the event of
disagreement, the right of either party to have recourse to an
arbitrator.
South Holland was not only confident that the contractual
arrangements between the parties were to be interpreted this way,
but that negotiations in respect of the additional costs deriving
from the architect's instruction had indeed concluded in a
settlement figure.
The arbitrator found in favour of South Holland on each step of its
contention. He concluded that the architect's instruction had
contractual effect and that in compliance with that instruction the
parties had negotiated an agreement for both the scope of the works
and the remuneration payable for the phase two works.
In reviewing all of these matters, His Honour Judge Thornton QC
decided that the arbitrator was correct. He had correctly concluded
that the architect's instruction in question had contractual
effect. It was not necessary in the circumstances to look for offer
and acceptance embracing the entire work scope and pricing, such as
would be involved when a new contract was negotiated and
finalised.
What occurred following the instruction issued under the original
contract was a piecemeal agreement of individual work items and its
cost. It was not necessary, therefore, for the entirety of the
bills of quantities, specification and drawings first to be
negotiated and then offered by one party as a composite package for
acceptance by the other party. In consequence, Hallamshire's appeal
was dismissed and the award of the arbitrator confirmed.