It is commonplace in the construction and engineering industries
for there to be a requirement to keep records of time and materials
spent on certain aspects of the work in justification for the
contractor's entitlement to be paid.
This requirement will obviously arise on time- and material-based
contracts, but may also arise where, as an element of the
evaluation process under a lump sum contract, a fair evaluation has
to be made of ordered variations or loss and expense incurred by
the contractor. Disputes will inevitably occur where the parties
fail to maintain a proper system of record keeping and a joint
protocol for agreeing the time and materials expended by the
contractor as the work progresses.
The recent case of JDM Accord -v- The Secretary of State for the
Environment, Food and Rural Affairs (DEFRA) examined the evidential
value of daywork sheets maintained by the contractor in accordance
with the contract to support payment claims, in circumstances where
the employer had failed to verify and approve those daywork sheets
at the time that the work was being carried out.
The dispute arose out of claims for works carried out by JDM
relating to cleaning and disease suppression at a large number of
locations throughout the UK during the foot and mouth epidemic in
2001. At the height of the foot and mouth crisis more than 10,000
vets, soldiers, field and support staff, and many thousands working
for contractors, were engaged in fighting, eradicating and
preventing further outbreaks of the disease. The work involved the
slaughter of animals, the preparation of burial sites for the
disposal of animal carcasses and the construction of the necessary
infrastructure to support those sites.
The first outbreak of the disease was confirmed in February 2001 at
an abattoir in Essex. The outbreak lasted for 32 weeks and by the
time that it had been finally eradicated in September 2001, six
million animals had been slaughtered and 2,000 premises, spread
through 44 counties, had been infected. The cost of the consequent
clean up and disposal operations, compensation payments and other
direct costs and losses was estimated at more than £3bn to the
public sector and more than £5bn to the private sector.
JDM's claim, totalling in excess of £5m, arose out of
extensive work carried out by it in 2001 on more than 160 different
sites in the south-west of England and in Wales. The size of the
operations carried out by JDM can be gauged from the fact that it
had already been paid in excess of £32m and the timescale over
which all of its work was carried out was between March and
December 2001. JDM was one of over 1,200 contractors engaged upon
similar works.
Initially DEFRA had entered into an agreement with JDM, in similar
terms to many other contractors, in which it was anticipated that
DEFRA would have a nominated representative based permanently on
each site who would record the times and activities carried out by
each employee and each item of plant engaged by JDM. A timesheet
would be signed each day by that representative and a nominated
employee of JDM.
However, despite having national contingency plans in place, it is
clear that the 2001 outbreak was of such unprecedented severity
that its extent and seriousness was not foreseen. Overwhelmed by
the scale of the spread of the disease, many sites had no DEFRA
representative, and on most sites no timesheets were verified or
authenticated by a DEFRA representative.
The verification procedure was clearly intended to preclude
disputes as to the number of chargeable hours actually performed.
Although jointly signed timesheets would not amount to conclusive
evidence of JDM's entitlement to payment for the particular number
of chargeable hours recorded on any timesheet, DEFRA would only be
able to challenge the content of the timesheets for payment
purposes to the extent that it could later produce evidence to show
that an inaccuracy or error had occurred.
In other words, had DEFRA properly verified and countersigned the
timesheets at the time they were submitted, the parties would have
been bound to proceed on the basis that the recorded chargeable
hours correctly represented the number of chargeable hours for
which JDM was entitled to payment.
By failing to verify and sign the timesheets, DEFRA was in breach
of contract. Judge Thornton QC took the view that it would be wrong
to allow DEFRA to take advantage of its breach of contract such
that it could make a more extensive challenge to the timesheets
than it could have done following their verification.
Having failed to challenge the timesheets at the time of their
submittal, DEFRA now carried the evidential burden of showing that
the contents of the timesheets were inaccurate.
In practical terms, since there were no other records made, DEFRA
would be restricted in its attack on the timesheets to showing that
they contained arithmetical or other patent errors, that they were
subject to some general error, such as not allowing for deductible
meal breaks, or were fraudulently produced such that no weight
could be placed upon them.
In conclusion, Judge Thornton was satisfied that the timesheets
should stand, without further proof, as accurate and reliable
evidence of the number of chargeable hours worked by JDM. This
would only be capable of being discounted if DEFRA produced
significant credible evidence as to how or why a particular group
of timesheets were to be considered inaccurate.