Bath & North East Somerset District Council can trace its
ownership of the site of the hot springs in Bath to a grant of
title by Queen Elizabeth I in 1590.
In 2000, the council undertook the restoration of the spa buildings
on the site for use as leisure and health facilities. It entered
into a contract under the standard JCT form with Mowlem for these
works, which were expected to be completed in 2002. Unfortunately
that did not happen.
By mid-2003, problems were apparent in the paint coatings that had
been applied to the pools on the site. The pools were leaking. The
council attributed responsibility to Mowlem's workmanship. Mowlem
responded that the fault lay elsewhere, in inadequate design or
specification of inappropriate materials.
Eventually the council instructed Mowlem to remove the entirety of
the paint finishes and associated fillers back to the substrate.
The instruction was given under the provisions of clause 8.3 of the
contract, which empowers the architect to instruct the contractor
to open up work for inspection or to arrange for tests of any
materials and goods.
Mowlem objected to an instruction for the removal of all paint
issued under the opening up and testing provisions of the contract.
It contended that the matter had moved on from there. Instead, it
requested that the instruction be given under clause 13, such that
the work would be treated as a variation to the contract
works.
Quite why Mowlem objected in this manner is not clear. If it was
subsequently proved that it was blameless, the JCT contract would
normally provide it with a remedy for extension of time and costs
regardless of which clause underpinned the instruction.
Nevertheless, Mowlem refused to carry out the work in accordance
with the instruction under clause 8.3.
The council defiantly stood its ground and gave notice to Mowlem
under clause 4.1.2 of the contract, indicating that Mowlem was to
comply with the instruction within seven days. In the event that
Mowlem failed to do so, the notice indicated that the council would
instruct others to carry out the work and the costs of so doing
would be charged to Mowlem's account.
Seven days later, instructions were duly passed to an alternative
contractor (Warings), which was refused access to the site
by Mowlem.
Escalating dispute
The next and perhaps inevitable stage of this escalating dispute
came when the council applied to the court for an injunction
restraining Mowlem from denying Warings access to the
site to carry out the paint
removal works.
That application was heard in the Technology and Construction Court
in October of last year and His Honour Judge Seymour QC granted the
council the injunction it sought. From there, last week the matter
was heard again in the Court of Appeal. Again, the council was
successful in obtaining its injunction.
Judge Seymour was clearly unimpressed with Mowlem's argument that
the situation had gone beyond testing under clause 8.3. He
completely missed the point as to the relevant use and consequences
of that clause. The decisive question, as far as he was concerned,
was whether or not an injunction should be granted "as a matter of
convenience" following the guidance of Lord Diplock, who said that
an interim injunction should be granted where the plaintiff "may in
the meantime have suffered harm and inconvenience for which an
award of money can provide no adequate recompense".
Mowlem's position in respect of this argument was that the contract
carried provisions for liquidated and ascertained damages to the
tune of £12,000 per week and, if it were proved in the long
run that Mowlem was at fault, then the council would be adequately
recompensed by the payment of those damages for the full period of
delay.
The council accepted that it would be bound in any claim for delay
by its contractual agreement regarding liquidated damages.
However, its true loss would be considerably higher if the project
were to be stuck on hold while these disputes were resolved. There
would be an indefinite stalemate while the parties disputed the
causation of the defect, and the council would suffer a significant
loss and damage which was in excess of the rate of liquidated
damages payable under the contract. Moreover, the council contended
that there would be a negative effect on economic regeneration
within the area and on public confidence in the council. The
council did not want to be associated with a project which had
moved from the status of "Eden" to "Dome".
Judge Seymour agreed with those propositions. So too did the Court
of Appeal. The liquidated and ascertained damages provisions of the
contract represented a cap on the recoverable damages the council
could obtain in the event of delayed completion of the project, but
did not for any other purpose constitute a fair measure of the full
loss that might be suffered by the council.
Having steadfastly ignored Mowlem's complaints over the use of
clause 8.3, the court held that Mowlem was in breach of contract by
refusing to permit the council to engage its own contractor to
carry out paint removal works. The agreement on liquidated and
ascertained damages was not an agreed price to permit Mowlem to
breach its contract.
The Court of Appeal therefore dismissed the appeal and upheld Judge
Seymour's decision to grant the injunction. The council was
entitled to choose any particular contractual step that it regarded
as open to it and there was no basis on which Mowlem could properly
complain that the council should have taken some other step. It was
obliged to give access to the council's contractor to carry out
remedial work.
All of which has proved to be something of a sideshow, since
immediately prior to the appeal the council finally issued the
variation instruction that Mowlem was looking for. Whether that
means that the question of liability for defects is now resolved is
quite another matter.