Hills Electrical & Mechanical Ltd entered into a subcontract
with Dawn Construction containing a 'pay-when-paid' clause.
Although such clauses have continued to antagonise many in the
industry, since the Construction Act there is no proper cause for
complaint. Section 113 of the Act provides that pay-when-paid
clauses are perfectly lawful, providing they only apply in
circumstances where the third party payer is insolvent.
Within four months of entering into the subcontract, the employer
under the main contract indeed became insolvent.
Dawn refused to pay further monies to Hills, relying on the
pay-when-paid clause of the subcontract. Not entirely happy with
this prospect, Hills commenced proceedings to recover some
£93,000 that it contended was due.
Hills did not argue that the pay-when-paid provision was unlawful.
Such an argument would not have taken it very far. Instead it
approached the problem from a different angle. Hills argued that
the final date for payment of the £93,000 had occurred a few
days prior to the insolvency of the employer. That being the case,
those monies should have already been paid to Hills before the
insolvency, and accordingly the pay-when-paid provision should not
bite.
In order to achieve that position, it was necessary for Hills to
contrive an argument that supported the contention that the final
date for payment had indeed passed at the date of the insolvency of
the employer. The subcontract provided that the final date for
payment should be 28 days from the due date of any interim payment.
Crucially, the statutory Scheme for Construction Contracts provides
that the final date for payment shall be only 17 days from the due
date.
This 11 day period was critical to Hills, for it straddled the date
at which the employer had become insolvent. Quite simply, if the
main contractor was permitted 28 days for payment of the sum due,
by that date the employer had become insolvent and the
pay-when-paid provision would bite. On the other hand, if only 17
days applied, the main contractor would have been obliged to make
payment before the insolvency of the employer and accordingly the
pay-when-paid clause would be irrelevant.
Hills needed to prove that payment should have been made within 17
days. It was, therefore, necessary for it to show that the
subcontract terms for payment were in some respect non-compliant
with the Housing Grants Construction and Regeneration Act, with the
effect that the entire payment provisions of the Scheme for
Construction Contracts should be imported into the subcontract.
Hills relied on Sections 109 and 110 of the Act. Hills' position
was that when a construction contract failed to contain terms that
comply with the requirements of Section 109 and 110, the whole of
the Scheme provisions came in to play in substitution for any
agreed contractual provisions regarding payment.
Hills argued that the subcontract between the parties failed to
provide dates by which the subcontractor should make applications
for payment. According to Hills, this was sufficient for the
entirety of the subcontract provisions to be dropped and replaced
by the Scheme, which would then allow for a final date of payment
of each interim amount within 17 days of the due date.
Dawn did not accept that the subcontract terms were deficient in
any manner, but argued that even if they were, the final date for
payment of any sum due to the subcontractor was a matter which had
been agreed within the subcontract. This did not fall to be
substituted by the provisions in the Scheme.
Hearing these matters in the Outer House of the Court of Session in
Scotland, Lord Clark had to decide the correct approach. The only
previous case which had directly touched on this question was that
of C&B Scene Concept Design -v- Isobars. There it had been
argued that the parties had failed to complete Appendix 2 to the
JCT form where it was necessary to select either alternative A for
lump sum payment, or alternative B for periodic evaluation.
Isobars had argued that if no mention had been made between
alternatives A and B, the entirety of clause 30 of the JCT contract
concerning payments must be swept away, to be replaced by the
Scheme for Construction Contracts. At first instance, the judge
held that this was indeed the case. The matter then came before the
Court of Appeal, but regrettably that part of the question was not
considered.
Relying upon the C&B case, Hills argued that it would create
chaos for payment provisions to rely both upon imported sections
from the Scheme and retained parts of the subcontract.
Lord Clark could not see that chaos would result. Section 110(1)
provided that the parties were free to agree the number of days
between the date a sum becomes due and the final date for payment.
In his judgment, the approach of the legislation was not as Hills
contended. The approach was simply to import into the parties'
contract the appropriate provision from the Scheme to make up for
any omission.
In consequence, the originally agreed subcontract period of 28 days
continued to apply. This meant that the date for payment did not
fall until after the employer had become insolvent, and thus the
pay-when-paid clause applied. Hills' attempt to recover the
£93,000 failed.