Letters of intent are widely used in the construction industry and
continue to cause considerable difficulty. It seems that the
procurement processes of large construction projects have become so
complex that contractors are generally able to mobilise
construction operations far more quickly than it is possible to
assemble the necessary contractual and commercial documentation for
the placing of a contract.
Indeed, the current trend towards partnering type arrangements,
while perhaps bringing certain benefits, may
be encouraging a relaxed attitude towards the placing of clear
and definite contracts before works proceed.
A letter of intent ordinarily expresses an intention to enter into
a contract at a future date, indicating that no contract is secured
by the letter itself. The reality is, however, not quite as simple
as that. As always, it is a case of relying on the facts of each
instance, as to whether the sending of a letter of intent can give
rise to any, and if so, what liability.
Where the letter of intent can be shown to be a "subject to
contract" type of arrangement, there will generally be no contract
between the parties, with the consequence that the contractor will
be obliged to complete such works as it has undertaken within a
reasonable time and be paid a reasonable price.
An example of this approach was found in the case of Galliard Homes
-v- J Jarvis & Sons in 1999. The parties had reached agreement
on all the matters that would normally be required for a contract
to be formed, but the contract preliminaries contained a clause
that very clearly stated the contract between the parties was to be
executed as a deed under seal. The Court of Appeal held that the
agreement between the parties did not have legal effect until a
formal contract, being a contract under seal, was signed by the
parties.
Different view of the facts
The Court of Appeal took quite a different view of the facts in the
more recent case of Harvey Shopfitters v ADI. Harvey submitted a
tender to carry out refurbishment works in properties belonging to
ADI.
Through its architect, ADI issued a letter of intent to Harvey,
confirming that it was its intention to enter into a contract with
Harvey on the basis of the tender sum and that the conditions of
contract would be those of the JCT Intermediate form.
Harvey was asked to accept the letter as authority to proceed, but
if for any unforeseen reason the contract should fail to proceed
and be formalised, then any reasonable expenditure incurred by
Harvey was to be reimbursed on a quantum meruit or reasonable price
basis.
Thereafter work continued, but no formal contract was prepared
incorporating the JCT Intermediate form. Disputes arose, and Harvey
claimed that the work had been carried out with an entitlement to
be paid a reasonable price, whereas ADI contended that a lump sum
contract had been formed.
The Court of Appeal held that by the time of the letter of intent,
the parties had agreed all issues and there was nothing left to
discuss or formalise. A contract had therefore been formed. The
mere fact that the parties had contemplated executing formal
documents did not detract from the clear intention of the parties
to be contractually bound.
Lord Justice Latham noted that the letter itself could not be read
in isolation. It formed the culmination of a process between the
parties that had resulted in an agreement as to price and all
material terms necessary for the commercial working of the
contract. All necessary ingredients for a valid contract were
present.
While the behaviour of the parties leading up to the issue of a
letter of intent may therefore be important in understanding the
effect of the letter, it is important to recognise that the
behaviour of the parties after the letter of intent will not
ordinarily be taken into account.
Interim payments
From commencement of the works, interim payments had been made to
Harvey pursuant to certificates issued in accordance with the JCT
Intermediate form.
Architect's instructions had been issued in accordance with the
requirements of the Inter-mediate form, and the final account had
been settled, taking as its starting point the tendered sum, again
all in accordance with the requirement of the Intermediate form.
Nevertheless, none of this was relevant in determining whether the
parties had intended to be bound by a contract incorporating the
terms of the Intermediate form.
It was understandable that the parties might manage their affairs
for interim payment, extension of time and the like by reference to
the terms of the contract they anticipated later agreement upon.
That did not, however, indicate agreement of the parties to the
formalisation of the contract.
Similar issues were examined earlier in 2003 in the case of Tesco
-v- Costain, where Judge Seymour said: "The fact that the parties
have behaved towards each other in anticipation of the conclusion
of a contract between them in the manner which would have been
appropriate if they
had in fact concluded the contract, concerning which they were in
negotiation, is of little value in resolving the issue of whether
there was in fact a concluded contract."