Adjudication is not always the quickest or cheapest way to resolve
construction disputes. In the case of Amec Capital Projects -v-
Whitefriars City Estates, it is recorded that the parties had spent
over £270,000 in conducting two adjudications in an attempt to
resolve payment disputes between them.
The court refused enforcement of both adjudications, leaving the
parties counting the cost and no further forward in resolving
matters between themselves.
His Honour Judge Toulmin QC commented that if either arbitration or
court proceedings in the Technology and Construction Court had been
started in May 2003, when the first adjudication had commenced, the
parties would probably have had a hearing and a decision on the
merits of the case by now.
Amec had been engaged under a letter of intent to carry out certain
preconstruction services for Whitefriars in connection with a
building development in Tudor Street, London.
The letter of intent formed the basis of a contract between the
parties incorporating the JCT 1998 standard form with Contractor's
Design. The letter had provided that the parties would negotiate a
second stage tender for the main building works.
Amec carried out preconstruction services on site for a period of
approximately three months. At that point, however, Whitefriars
determined Amec's contract because the parties could not agree on
the second stage tender. By that stage Amec had submitted invoices
for £204,000 that had been paid, and further invoices for a
sum in excess of £500,000 that had not been paid.
Negotiations between the parties failed to resolve the impasse in
connection with these payments and almost two years later Amec gave
notice of adjudication for the wrongful withholding of monies due
to it in the sum of approximately £500,000 plus VAT. An
adjudicator was duly nominated by the Royal Institute of British
Architects (RIBA), who decided in favour of Amec for the full
amount. Whitefriars failed to comply with that decision which then
came before His Honour Judge Lloyd QC on enforcement proceedings.
Judge Lloyd refused to grant enforcement of the decision. He held
that an alternative adjudicator had been named in the contract
between the parties, and, therefore, the adjudicator appointed by
RIBA had not been validly appointed and had no jurisdiction to make
the decision.
It emerged soon after that hearing, however, that the adjudicator
named in the contract between the parties had sadly died some time
before the dispute had been referred to adjudication. Armed with
that knowledge, Amec recommenced the adjudication applying to RIBA
a second time for the appointment of an adjudicator, suggesting
that the first adjudicator might be renominated in the interests of
saving time and costs. RIBA duly obliged and a second adjudication,
essentially on the same facts, was commenced.
This time however, Whitefriars responded with a notice of a
withholding and a counterclaim. It advised that since the contract
had been terminated between the parties, the situation that
prevailed was that Amec would not be entitled to any further
payment until another contractor completed the works. Whitefriars
suggested that Amec would only become entitled to the difference,
if any, between what it would have earned by completing the
contract and what Amec's breach had cost the employer.
This brazen approach appeared to ignore the fact that the
determination had been brought about by both parties' failure to
agree terms for the carrying out of the building works. Whitefriars
also indicated that it would bring a substantial counterclaim,
which it valued in the amount of £1.2m.
Amec refuted allegations that it was in repudiatory breach of the
preconstruction contract and repeated that its final account had
been submitted for more than two years and that in the absence of
any response or a valid withholding notice at that time, the
account had become payable.
The adjudicator rejected Whitefriars' counterclaim and set-off,
saying that it was a separate and independent claim and, therefore,
outside his present jurisdiction. He ordered that Whitefriars
should pay Amec the full amount claimed plus VAT. Once again,
Whitefriars refused, and the parties appeared in court for
enforcement of the adjudicator's decision.
Whitefriars resisted enforcement on a number of grounds. It
complained that the reappointment of the earlier adjudicator had
led to a serious risk of bias. Judge Toulmin noted that while it
might have made good sense for RIBA to appoint a different
adjudicator on the second occasion, he was not ready to conclude
that, taken in isolation, there was a real possibility that the
adjudicator was biased in reaching his decision in the second
adjudication merely because he had already reached a decision on
the same or similar facts.
A further objection from Whitefriars was, however, to be regarded
more seriously. Whitefriars complained that the adjudicator had not
disclosed to the parties advice that he had received from his legal
advisers in the first adjudication in relation to the withholding
issue.
Judge Toulmin noted that when an adjudicator is seeking advice from
a third party, it is essential that he informs the parties how he
has formulated the question and that he discloses the substance of
the advice giving the parties an opportunity to comment on it
before he reaches his decision. This had not happened in the
present case and this was contrary to natural justice.
In conclusion therefore, the decision of the second adjudication
was not enforced for reasons that were quite independent of the
underlying merits of the case, proving that it is the very fast
track nature of adjudication which may on occasion prove to be its
undoing.