In July last year, I reported the case of Hurst Stores &
Interiors -v- ML Europe Property, which
concerned whether a purported settlement agreement was binding on
the parties (CJ 30 July 2003).
ML Europe was the corporate vehicle used by Merryl Lynch for the
development of its new European headquarters in the City of London.
The works were being procured on a construction management
arrangement and Hurst was contracted as package contractor for
toilet fit-out works in the amount of approximately £2.4m. In
the event, the works were extensively altered and delayed, and
shortly after completion, almost a year later than planned, Hurst
prepared a final account that claimed a total of £6.5m for the
works.
ML's construction manager, Mace, was unimpressed with the final
account document. It was returned to Hurst as rejected. Mace
claimed that it should be ignored since there was a prior agreement
between the parties in settlement of the final account for the
package works. Whether Mace was correct in that assumption was the
subject of a decision of the Technology and Construction Court in
June last year.
At the heart of the dispute lay a procedure that Mace had
instituted for the commercial management of all trade contract
packages on the project. The contract provided that Mace would
issue to Hurst interim statements of accounts (ISAs) each month,
which would detail all instructions issued to Hurst. Hurst was
required to value the ISA and return it within seven days,
accompanied by all necessary information, measurements and
calculations.
The contract went on to say that Hurst would be required to signify
its agreement and acceptance of the valuation of the instructions
detailed in the ISA.
As the works progressed, more than 500 instructions were issued to
Hurst, and the ISAs therefore became weighty documents.
Nevertheless, Hurst's project manager diligently returned the form
each month duly completed and signed, believing that by his
signature he was indicating agreement to the net value of the
instructions received by Hurst, but no more than that.
Six months before the works had finished, an ISA was issued by Mace
with two significant changes. First, the word "final" was
substituted for "interim". And second, in place of the standard
wording normally included on the last page, a different last page
had been inserted that said that the calculated amount payable to
the contractor was to be accepted by Hurst in full and final
settlement of all claims arising out of, or in connection with, the
trade contract works.
Hurst's project manager paid little attention to these changes and
proceeded on the basis that it merely reflected the prior
agreements already reached between the two parties in previous
ISAs. He signed and returned the document to Mace.
When the matter came before an adjudicator, he held that that
document was binding on Hurst and that no further claims could be
entertained for events that occurred up to the date of the
document. This was a shocking finding for Hurst, for it meant that,
among other elements of its final account, its claim for loss and
expense amounting to £2.5m would effectively be barred.
The dispute proceeded to court where Hurst argued that the document
should not be binding on it for two principal reasons. First, Hurst
argued that its project manager did not have authority to enter
into such an agreement because it was outside the terms of the
trade contract.
Second, Hurst complained that the document was entered into on the
basis of a unilateral mistake on the part of its project manager
and that the document should accordingly be rectified, so as to
remove the reference to it being made in full and final settlement
of all claims accruing up to the date of the document.
On both those points, the court agreed with Hurst. The project
manager acting for Hurst did not have authority to vary the
contract. No authorised representative of Hurst had agreed to such
a document and accordingly the agreement shown in it could not be
binding on the parties. The court also agreed that the document
should be rectified to remove the words that attempted to make the
document a full and final settlement of all claims.
At the beginning of this month, these matters were heard again in
the Court of Appeal.
ML challenged the decision of the earlier judge, arguing that the
evidence did not support the finding that Hurst's project manager
had been mistaken as to the nature of the document that it had
signed.
The Court of Appeal was not prepared to overturn the findings of
the earlier trial judge. There was ample evidence for the judge to
reach the conclusion that Hurst's project manager had been mistaken
as to the true nature of the document that Mace had prepared as a
final statement of account.
The judge was therefore entitled to rectify the document and
entitled to find on the evidence that Hurst's project manager had
no authority to commit Hurst to an agreement that effectively wrote
off large sums that might otherwise be proved to be due under the
terms of the trade contract.
The appeal was therefore dismissed.