This year marks 150 years since the most celebrated common law case
of all time, the 1854 decision of Hadley v Baxendale. Hadley is the
one case that every lawyer practising in common law jurisdictions
throughout the world will have read and applied. Its teaching is so
universal and basic that many law tutors will mark a student down
if he or she merely trots out the case. Showing an understanding of
the principles in a wider context will be expected. In the past 10
years in the UK alone, it is said that Hadley has been cited in 139
judgments. Many of those will have concerned construction
disputes.
As is the case with many important legal decisions, the cause in
Hadley was trivial. Joseph and Jonah Hadley were the owners of a
flour mill in Gloucester. The Hadleys were businessmen at the heart
of the industrial revolution. They had installed steam-driven power
to their waterfront mill, bringing cheap imports of grain, massive
throughput and previously unheard of profits in flour milling.
Then disaster struck. The main shaft to the steam engine broke. A
replacement shaft could only be made by a company in Greenwich, and
in order to do this, the company needed the broken shaft to take
accurate dimensions. Since the mill was shut down, the Hadleys had
to move quickly to get the shaft from Gloucester to Greenwich. They
contacted Pickfords, which promised that for a payment of
£2-4s, it would deliver the shaft to Greenwich by the
following day.
In 1854, Pickfords was the biggest carrier around. It could trace
its origins back to the late 17th century. In 1817 however, at the
point of bankruptcy, Pickfords had been taken over by Joseph
Baxendale, who together with a small group of associates, had
rebuilt the business with remarkable success, taking considerable
advantage of the emergence of the railways.
Despite this commercial standing, Pickfords did not perform well
for the Hadleys. By some unspecified neglect, the broken shaft was
not delivered to Greenwich for several days. The consequence was
that the Hadleys did not receive the new shaft for several days
after they would otherwise have done, delaying the working of the
mill.
The Hadleys claimed that they had been obliged to buy flour to
supply some of their customers, had been deprived of profit and had
been unable to employ their workmen, to whom they were compelled to
pay wages during the extended closure of the mill. They sued for
£300 damages.
Baxendale objected that the damages claimed were too remote and
that it could not be liable. The Court of Exchequer agreed. Since
Baxendale did not necessarily know that the mill would be idle
until the shaft could be returned (there might have been a spare
shaft or there might have been other reasons for the mill being
shut down during that period), Baxendale could not be liable for
those damages.
The opinion of the court became known as the "foreseeability" test.
You cannot be held liable for losses that you could not reasonably
have anticipated.
The famous rule that was set out in the case is: "Where two parties
have made a contract that one of them has broken, the damages that
the other party ought to receive in respect of a breach of contract
should be such as may fairly and reasonably be considered either
arising naturally, ie, according to the usual course of things from
such breach of contract itself, or such as may reasonably be
supposed to have been in the contemplation of both parties at the
time they made the contract as the probable result of the breach of
it."
The rule therefore has what has been called two "limbs". The first
limb assumes that the parties have knowledge of certain basic
facts. Defendants will be held liable for damages that arise
according to the usual course of things. The second limb, on the
other hand, requires additional specialist knowledge by the
defendant. Since Baxendale did not in fact know that the mill would
be shut down until the shaft was replaced, he could not be liable
for damages that resulted from that closure.
A more recent example is found in the case of Balfour Beatty v
Scottish Power, where the latter had agreed to supply temporary
power for Balfour's concrete batching plant.
Balfour was constructing an aqueduct by continuous concrete pour,
and as a result of a power failure, had to demolish what had been
constructed and start again.
It claimed the cost of doing so as damages. It was held that
Scottish Power did not, and was not presumed to, know of the
practice of construction by continuous concrete pour and the claim
failed.
The significance of Hadley is that it came at a time when the law
of contract was only beginning to emerge. Previously, commercial
relationships were regulated by custom, not by individual
agreement. Hadley fixed a basic contract rule that has stood the
test of time, which is both predictable and flexible. On another
occasion, the power company may be aware of the requirement for
continuous concrete batching. It had better take precautions to
avoid power failure or charge more in exchange for the risk.
Hadley is often cited in two other areas of construction law.
First, in connection with the exclusion of liability for
consequential loss that is often found in construction contracts.
The courts have found that generally, consequential loss is likely
to approximate to loss within the second limb of Hadley. In other
words, despite a clause in the contract excluding liability for
consequential loss, the claimant will still be entitled to recover
all his losses that can be shown to arise naturally.
Second, the courts have made it clear that contract provisions for
loss and/or expense, as found in the JCT contracts for example, are
to be equated with damages under the first limb of Hadley.
Contractors that include in their loss and expense claims such
items as exceptional profit or overheads should bear in mind this
150-year-old law.
The Hadleys' mill is being restored this year as part of the
redevelopment of part of Gloucester's historic docks. It seems the
common law rule on foreseeability of damages will be around as long
as the old mill.