Post-repudiation adjudication


The recent case of Connex South Eastern -v- MJ Building Services Group considered the requirement for an agreement to be in writing within the meaning of Section 107 of the Construction Act. It also examined whether a party has the right to refer a dispute to adjudication under the provisions of the Construction Act if the contract has been discharged by repudiation.
MJ is a contractor experienced in installing closed circuit television systems. It had entered into a contract with Connex to provide CCTV systems for 50 stations throughout the franchise areas that Connex held for the rail networks in Kent and Sussex. As is so often the case with projects of this type, the procurement processes were appallingly lax. No written order was issued by Connex and no contract between Connex and MJ was signed. MJ had responded to an invitation to tender, following which a meeting had taken place between the parties, during which a representative of Connex had instructed MJ that it was to commence work. The minutes of the meeting recorded that Connex had given an oral instruction that the project was to be carried out immediately.
ADVERTISEMENT
 

Soon after commencing the works, Connex wrote to MJ stating that all CCTV works were to be suspended until further notice. Meetings were held to discuss revised programmes and schedules of work and eventually the works were resumed. A year later however - by which time Connex had been acquired by another company - MJ received instructions that no further works were to be commenced. The works were brought to a halt and MJ made claims for approximately £200,000 for work carried out to date. The parties failed to reach agreement upon outstanding payments and, in due course, MJ wrote to Connex saying that it had repudiated the contract and that MJ had accepted that repudiation. One and a half years later, MJ commenced adjudication proceedings.
Before the adjudication proceeded, the parties agreed to refer certain points to the court for declarations as to whether adjudication was appropriate in the circumstances. Connex argued that there was no agreement between the parties recorded in writing as required by Section 107 of the Construction Act. It also argued that MJ no longer had any statutory right to adjudication under Section 108 of the Act in circumstances where it had argued that the contract was discharged by repudiation.
Section 107 of the Construction Act provides that the Act will only apply where the construction contract is in writing, or if the agreement is evidenced in writing. Connex relied upon the case of RTJ Consulting Engineers -v- DM Engineering and argued that, to fulfil the requirements of Section 107 of the Act, the complete agreement between the parties, or alternatively at least all material terms, must be in writing. MJ argued that whether or not that was correct, it was manifestly not the intention of Parliament to exclude from the jurisdiction of an adjudicator an agreement solely because it contained implied terms.
His Honour Judge Richard Havery QC confirmed that the instruction to commence work constituted an acceptance of MJ's tender. Judge Havery concluded that the minutes that recorded the instruction to proceed were written with the authority of the parties and therefore constituted written evidence of the acceptance of the contract falling within Section 107(4) of the Act.
The next question Judge Havery had to address was whether acceptance of repudiation of an agreement brings
to an end a provision for adjudication. Connex argued that
it was an abuse for MJ to start adjudication proceedings one and a half years after it had argued that it had accepted the repudiation of the contract on the part of Connex. It was accepted that, under Section 108 of the Act, a party is entitled to give notice of its intention to refer a dispute to adjudication at any time. Connex argued however, that the right arose only during the currency of the contract and the words "at any time" had to be construed with that in mind. It was plain that Parliament did not mean that an adjudication notice could be given a hundred years after the dispute had arisen.
Judge Havery was satisfied that while no limitation period is laid down for instituting an adjudication, a limitation defence must be taken into account
by the adjudicator. It was well established that an adjudication could take place after works under a contract had been completed and he was satisfied that, as long as there was a possibility of a dispute arising under the contract, the right to seek adjudication would remain. There was no reason not to give the words "at any time" their plain and natural meaning.
Judge Havery rejected the argument that adjudication was intended only to relieve cash flow problems arising during the course of a contract and could not be used in the case of a dispute where a repudiation had been accepted.
In consequence, the declarations sought by Connex were refused and the adjudication could proceed to deal with matters in dispute between the parties.


ADVERTISEMENT

 
ADVERTISEMENT