Jarvis is running three months late on its £30m fire station
PFI in Tyneside.
Six new-build fire stations were due to be completed in June, but
will not now be ready until October at the earliest due to a
reported slow down in work and subcontractors downing tools over
late payment.
A Jarvis spokeswoman said: "We are running a few weeks behind
schedule. If you go around the sites there is a lot of work going
on. We are working with the fire authority.
"Work was virtually halted a month ago, but the amount of labour on
site has been picking up dramatically and continues to do so.
"We would expect the first station to open in the early part of
October."
A Tyne & Wear Fire Authority spokesman confirmed the PFI
project was running late, although he was confident the project
would be completed by the agreed deadline.
"We had a recent meeting with Jarvis and we were reassured that
everything is now back on track and the new deadline would be
reached," he said.
However, one project source told CJ: "Work has virtually ground to
a halt across all the sites. Some of the sites have only one worker
carrying out work.
"Many subcontractors stopped work and walked off site after they
became worried that they wouldn't be paid by Jarvis due to its
financial difficulties. Looking at work in progress at the moment,
it is unlikely that Jarvis will meet the October deadline."
The Fire Authority spokesman added: "We need to discuss the issue
[of compensation claims] after completion and see what clauses are
in the contract."
The six stations, in the order in which they are to be opened, are:
North Moor Lane, Sunderland; Market Lane in Swalwell; Colby Court
and Union Road in Newcastle; Dryden Road in Low Fell, Gateshead;
and Glover Road in Washington.
A new headquarters in Barmston Mere in Washington and a technical
service centre on Gateshead's Quayside are also being built.
Jarvis was awarded the contract in December 2002 after beating
Kajima.