Resolving disputes on construction contracts is costly and time
consuming. In certain cases, the time that management devotes to
the dispute may also be severely disruptive to the ongoing
business. The parties will therefore want to take into account the
recoverability of the cost of its management and employees in
connection with the dispute resolution process.
In December 2002 I reported the case of Amec Process & Energy
-v- Stork Engineers & Contractors, which dealt with whether
management time could be recovered as costs in arbitration or
litigation proceedings. It was always thought that the successful
parties' direct costs incurred in using its own employed staff to
prepare material for the case would not be recoverable as costs in
the proceedings.
However, that case appeared to indicate a softening of the court's
attitude in awarding costs to a successful litigant. Judge Thornton
clearly felt that the Civil Procedure Rules allowed him to widen
the category of employees that could be reimbursed in the event of
a successful litigation. This included Amec's own personnel and
agency staff, which had been engaged to undertake much of the work
involved in collating, analysing and presenting the primary and
supporting evidence to be used by the expert witnesses.
Contract breaches
An alternative to recovering management costs as costs of the
proceedings would be to seek to recover such costs as a head of
damages for breach of contract. This issue was examined in April
2003 in the case of Phee Farrar Jones -v- Connaught Mason.
Phee is a recruitment consultancy that had engaged Connaught to
carry out some refurbishment works on its office premises. During
the
carrying out of those works, a flood occurred, causing extensive
damage to the building. Connaught admitted liability for the flood,
which caused a significant delay to the completion of the
refurbishment works. As part of its claim against Connaught, Phee
included a claim for 90 hours of a manager's time expended in
organising a move to alternative accommodation.
It would normally be thought that managerial expenses such as this
could be claimed as damages if the claimant was able to establish
that, as a consequence of the other party's breach, the claimant's
trading was disturbed in a way that led to the expense being
incurred. In a decision that appeared to show a more restrictive
approach, Judge Toulmin rejected Phee's claim. There was no
evidence that income generating opportunities were lost as a
consequence of the manager being required to organise the move to
alternative accommodation and Phee had not demonstrated that the
manager's costs were discrete expenses that would not otherwise
have been incurred.
Turning point
This decision appears to have been in stark contrast to the
approach of Lord Drummond Young in the Court of Session in Scotland
two months earlier in the case of Euro Pools -v- Clydeside Steel
Fabrications.
Euro Pools designed and installed machinery and pipework for the
circulation, pumping, heating, filtering and treating of water in
swimming pools. It had been engaged to install filtration systems
for swimming pools being constructed at leisure centres in
Burntisland in Fife and East Molesey in Surrey, and had
subcontracted with Clydeside to fabricate and supply the filtration
tanks required for each installation.
These were expected to have a working life of up to 40 years and,
critically, were to be lined internally with high build epoxy as an
anti-corrosive lining. Shortly after installation it was discovered
that the tank linings had failed and that the walls of the tanks
were suffering widespread corrosion.
Euro Pools claimed the costs of remedial works carried out by
specialist contractors it brought in, and also claimed that some of
the work involved in investigating, decommissioning, and
recommissioning the filters had been carried out by its own
employees, who were diverted from other contracts for this
purpose.
This included the time and travel costs of one of its site
engineers and its managing director, both of whom were claimed on
daywork rates.
Euro Pools argued that had these employees not been engaged in the
rectification works, they would have been able to earn income at
higher charge-out rates.
Clydeside countered that any such losses must be traced through to
identifiable financial loss such as the additional cost of
completing other contracts. For example, in relation to the
managing director, there was no suggestion that he had been
deflected from other remunerative activity.
His salary would have been paid by Euro Pools whatever he did, with
the result that the company incurred no extra costs simply because
he had to work harder.
Lord Drummond Young rejected these arguments. He was satisfied
that, if employees are required to perform additional work in
consequence of a breach of contract, the work in itself represents
a loss to their employer. It was quite wrong to confuse
establishing that loss with the quantification of the loss. The
claimant was being deprived of services that its employees were
otherwise engaged to carry out, and that was sufficient to
establish the existence of a loss.
Objective approach
As to the quantification of that loss, an objectively reasonable
approach was to be taken. The employer was entitled to make a
charge that reflected both employment costs and overheads such as a
daywork rate. Subject to providing evidence of those costs, Euro
Pools was entitled to reimbursement on this basis.