The resolution of disputes on large construction and engineering
contracts increasingly involves the use of computer-based delay
analysis techniques to assist in the identification of the cause of
critical delay to a project and, in the more sophisticated cases,
to assist in the computation of claims for lost productivity.
While the industry is becoming more and more familiar with the use
of the tools and techniques employed in the process of delay
analysis, unfortunately at present there is very little common
agreement upon their correct application.
As the courts become more familiar with delay analysis techniques,
it is likely that there will be an increasing number of reported
cases addressing these issues, giving guidance to delay analysts as
to the preferred approaches to take and censuring experts who fail
to present cogent and balanced evidence that assists the
court.
An example is the recent case of Skanska Construction v Egger
(Barony) where Judge Wilcox was required to take account of the
evidence of expert delay analysts in arriving at the quantum of
damages. The contract between Skanska and Egger has created a
long-running legal battle between the parties.
Egger is a subsidiary of an Austrian family-owned company which
produces chipboard and other timber-based products at several
factories throughout Europe. It entered into a contract with
Skanska for the design and construction of a
factory to be built in East Ayrshire in Scotland.
Skanska agreed to undertake design development, management and
construction of the factory for a guaranteed maximum price of
£12m. Egger took direct responsibility for the supply and
installation of the specialist plant and equipment.
Particularly difficult
The contract was particularly difficult. By completion, Skanska was
making claims in the order of a further £12m relating to what
it argued were extras to the contract. There was a counterclaim by
Egger for more than £4m. In January 2003 I reported a decision
of the Court of Appeal where the court had reviewed earlier
decisions concerning responsibility for claimed additional works
arising out of design and development.
Following those earlier judgments concerning liability, Judge
Wilcox held a separate trial to hear evidence concerning quantum,
including the evidence of two expert delay analysts concerning the
delay suffered by certain Skanska subcontractors leading to loss
and expense claims which Skanska sought to pass on to Egger.
Judge Wilcox clearly preferred the evidence of Skanska's expert who
had prepared an analysis which he described as "accessible". He
described the characteristics of a good planning expert as someone
who was objective, meticulous as to detail and, importantly, not
hide-bound by theory when demonstrable fact collided with computer
programme logic.
Severely critical
Apparently this could not be said of the evidence provided by
Egger's programming expert. Judge Wilcox was severely critical of
his evidence on a number of levels. First, he made clear his
frustration with the complexity of his report. It ran to several
hundred pages supported by 240 charts. Egger's expert had been
supported by a team of assistants and it appears that the report he
had prepared was too complex and extensive for the court to
assimilate easily.
More critically, however, Judge Wilcox commented that the report
had largely been based upon factual matters provided third-hand
from employees of Egger, such that, perhaps understandably, the
expert was not entirely familiar with all
the details.
Judge Wilcox commented that the extent of reliance upon the
untested judgment of others in selecting and characterising the
data for input into the computer programme, however impeccable the
logic of that programme, adversely affected the authority of the
opinion based upon such an exercise.
Judge Wilcox gave an example of evidence which had been made
available to Egger's expert that contradicted the evidence upon
which he had based his report. Despite this, the expert had refused
to change his view, which clearly irritated Judge Wilcox, who
commented that it was surprising that there was not sufficient
intellectual rigour to admit the possibility of doubt.
Other failings in Egger's expert's evidence were highlighted. Judge
Wilcox observed that the reliability of a sophisticated
delay-impact analysis is only as good as the data put in. The
expert had made errors in reconstructing the initial contract
programme in a computer-based network form.
Those errors meant that the programme adopted by the expert could
not be used as a reliable base line. Similar criticisms were made
of the expert's approach to the construction programme, which he
had based upon a master programme prepared by Skanska, even though
this had become virtually redundant from the outset.
Heart of the matter
Judge Wilcox commented that at the heart of the matter lay the
expert's power of selection of facts and interpretive judgement of
them. This being the case, it was crucial that the expert could
demonstrate that he applied an objective and balanced approach to
the evidence.
That balanced approach needed to be applied, for example, when
dealing with the vexed problems of concurrent delays. Egger's
expert had taken the view that where there was a delay that Skanska
did not claim to be the responsibility of Egger, he had assumed
without further investigation that Skanska was accepting liability
for the event.
Judge Wilcox described this as applying the logic of Humpty Dumpty
and with that searing observation, rejected the evidence of Egger's
expert, holding substantially in favour of Skanska.