Last week in Contract Journal I examined the review that has been
carried out under the chairmanship of Sir Michael Latham into the
adjudication provisions of the Housing Grants Construction and
Regeneration Act.
This review will form the basis of a consultation with the industry
that the Department of Trade & Industry (DTI) is expected to
put in place early next year with a view to amending the
legislation where a reasonable consensus can be obtained.
The review also examined the payment provisions of the Act. The
points raised within this part of the review will be included
within the industry consultation. The working group looking into
the payment issues found it more difficult than the adjudication
working group to obtain unanimity. Nevertheless, a number of
specific recommendations have been made.
First, and perhaps most importantly, the review has recommended the
removal of section 110(2) of the Act which requires the paying
party to give a notice, not later than five days after the date on
which a payment becomes due under the contract, specifying the
basis for and the amount of the payment proposed to be made.
Removal of section 110(2) would require a redrafting of section
110(1) to define more clearly what is intended by "an adequate
mechanism for determining what payments become due and when".
These provisions have caused considerable confusion since they
first came into force some six years ago. At the outset some
observers concluded that the paying party's failure to issue a
payment notice would have the effect that the amount applied for by
a contractor or subcontractor became immediately due with no right
of enquiry into the correctness of that amount.
Quickly dispelled
That notion was quickly dispelled by the courts with the
consequence that a failure to serve a payment notice effectively
carries no sanction against the paying party. The result has been
that the requirement for a payment notice is frequently ignored
within the industry. The aim that lay behind the initial drafting
of the provision was that paying parties should set out clearly and
in reasonable detail what they intended to pay and what they were
refusing to pay, rather than leaving everyone in the dark by
applying 'on account' payments. That aim has largely been lost, but
it is surprising steps cannot be taken to strengthen the
requirement, rather than simply to remove it.
Similarly, the concept of a mechanism to determine when payments
become "due" under the contract has created confusion. The "due
date" is not the date at which the payment will be made, neither is
it necessarily the date at which, or up to which, the payment
entitlement is to be ascertained. These difficulties are compounded
by the fact that many contracts and subcontracts do not require the
contracting party to make an application for payment, although
plainly this is what generally happens within the industry. It is
clear that much would be gained if these statutory provisions
reflected more clearly commercial practice.
Next, the review has recommended that the right to suspend works in
the event of non-payment should be supplemented by a right to
reimbursement of the costs of suspension and remobilisation.
Moreover, the review has recommended that the right to suspend
should continue for a reasonable period after the disputed amount
has been paid, such that the party effecting the suspension is not
disadvantaged by the delay and costs incurred during a period of
remobilisation of its site activities.
A further point considered by the review is the question of
cross-contract set-off. The conclusion is that that this should be
prohibited subject to preserving the common law rights of equitable
set-off. Equitable set-off is available when a cross-claim is
closely connected to the claim, for example, where a claim for
delay damages is set off against a claim for the value of work
done.
Contractual set-off provisions often go further than that, by
allowing a paying party to set off claims under one contract
against payments that are to be made under a different contract. It
is provisions such as these that the review has recommended be
prohibited.
In addition to these points the review group was unable to reach
consensus on a number of equally important topics. For example, the
review examined the practice of including "pay when certified"
clauses in contracts. These clauses have a similar effect to "pay
when paid" clauses which were made unlawful by section 113 of the
Act. Finding a workable solution to this problem will be difficult,
not least because some forms of procurement, such as management
contracting, rely upon a third-party certification process for the
payment provisions to work.
Current regime
The group also considered whether the current regime should be
retained whereby pay when paid clauses are deemed acceptable in the
event of the insolvency of the upstream paying party.
Another area considered by the review was whether the Act should be
strengthened under section 111 such a withholding notice should
carry a requirement to provide adequate detail of the reasons for
withholding payment.
While it is admitted that many withholdings are made without
appropriate detail, it seems unlikely that an amendment to the
legislation in this area would give rise to anything other than
more fertile ground for disputes.
The full text of the report by Sir Michael Latham's review group
can be found on the DTI's website.