15:22 03 Jul 2007
|
A subcontractor has lodged a claim of nearly £1m against Amec Capital Projects for loss and damage, after it claimed the main contractor continually disrupted and delayed its works.
Barrett Ceilings was originally subcontracted by Amec to design, manufacture and install cedar rain screen cladding to two new residential blocks at the University of Cambridge on 10 March 2004, having started on site on 1 September 2003. But it did not fully complete the works until 13 September 2004.
In a writ filed in the Technology and Construction Court, Barrett claimed that its own work was beset by delays for which it bore no responsibility.
And the subcontractor contended that Amec had acted in breach of contract because it failed to pay the sums due to it in relation to the delays and disruption. It also claimed Amec had made variations for which it had not been properly compensated
The subcontractor has so far received £60,000 from Amec in relation to acceleration costs it incurred on the main contractor’s instruction.