10:10 15 Oct 2009
|
For firms involved in construction disputes, having an adjudicator decide in their faviour may seem an ideal outcome. However an adjudicator’s decision does not necessarily mean the other party will pay up – indeed, in some cases they may not have to. Steven Bate explains how firms can legitimately resist paying – and what claimants can do to safeguard their rights.
If the contract is a proper construction contract under the Housing Grants Construction and Regeneration Act 1996, then it contains implied terms permitting adjudication. If it is not a proper construction contract under the Act, the courts will not enforce an adjudicator’s decision - unless there are standalone and effective provisions within it which allow adjudication.
To be a construction contract it must, amongst other things, provide for the carrying out of construction operations and must not be excluded. For example, the head contract in a PFI deal is not a construction contract and neither is a contract for the extraction of oil or natural gas.
If all of the terms of a contract are not in writing, then again it does not count as a construction contract for the purposes of the Act. If this is the case, again the courts will not be able to enforce an adjudicator’s decision unless there is an effective standalone set of adjudication rules within it.
This is particularly a problem for sub-contractors whose sub-contracts are ‘back to back’ with the main contract. In this case the subcontract usually contains a term that deems that the sub-contractor has seen the main contract and is bound by its conditions. Subcontractors often never see the main contract and may not realise that the provisions within it are different to those in the subcontract or implied by the Act. If the subcontractor starts adjudication under rules that are not in the main contract the courts will not enforce.
If there is a real risk that the adjudicator was biased, the courts will not enforce.
If the adjudicator fails to give each side a fair crack at the whip for putting their case forward or if he fails to give them the chance to comment on his findings - classically, doing his own delay analysis - then the courts will not enforce.
As long as the adjudicator answers the right question – in other words, stays within the bounds of the question put to him for resolution - then his decision is enforceable, even if he makes a complete hash of it. If the adjudicator answers a question that was not put to him or otherwise exceeds the bounds of his jurisdiction then the courts will not enforce.
If the ‘winning party’ is impoverished then the courts may order that the enforcement be postponed. If this happens, the losing side will usually have to pay the amount into a specially designated court bank account where it will sit until the dispute is resolved. Usually it is possible to then negotiate the release of these funds for a discount.
If at the time that the adjudication is started the other side has not had the chance to respond, or has indicated that it needs more information, then a dispute may not have ‘crystallised’. Often this is the case with interim payment disputes where the creditor wants to start an adjudication before the final date for payment. In these circumstances the court will not enforce a decision and adjudicators have been known to resign once this is pointed out.
If there is a series of disputes under the same contract, for example for subsequent interim applications for payment, then it may be possible to ask the court to refrain from enforcing an earlier decision because a later decision may be set off against it.
The contract may specify the identity of the adjudicator or which body is to nominate him. In some cases where the parties have appointed the wrong adjudicator or nominating body - in one case the body named did not even exist - the courts have refused to enforce. There have also been problems where a named adjudicator has died.
The Act provides for a tight timescale of 28 days from the referral notice for the adjudicator to publish his decision, although this may be extended by the parties. If the adjudicator fails to publish his decision within this or any extended timescale the courts may refuse to enforce.
If another adjudicator has already given his decision on a dispute then the courts cannot enforce.
Steven Bate is a construction and engineering partner with law firm DWF and a specialist in adjudication. Earlier this month, DWF launched the first 'no win, no fee' service for construction.