Ok i thought i'd seen it all

Last post 10-16-2009 21:39 by Stock... 1 replies.
Page 1 of 1 (2 items)
Sort Posts: Previous Next
  • 09-18-2009 22:37

    Ok i thought i'd seen it all

     This is a traveller given to me on a temp foul drain run from the site offices!

    The Engineer was fresh out of Uni.

    We're going to abuse him on this job!

     

     

    He ordered 4 inch pipe and 6 inch manholes chambers,

    After the first dig he lowered everything 500mm!

    The pipeline and two manholes started off 90 mm low then 250 mm high without moving a thing!

    Then just when i thought it can't get any worse the he checked the fall on a plastic duct for an electric cable!

  • 10-16-2009 21:39 In reply to

    Re: Ok i thought i'd seen it all

    Had an engineer mark out a bridge with a meter off set on all points,when the abutments went in there was a discrepancy of a meter for the beams,he the engineer never could really explain that one or the storm water line that was 600mm too deep, the list is longer than my arm.